Metrolinx Continues Its Pursuit of Hydrogen Trains

Metrolinx has released a long study about the feasibility of using electricity generated from hydrogen fuel cells as an alternative to conventional railway electrification with overhead wires. The “Hydrail” project page contains links to both a quicky “fact sheet” and to a 353-page report. The report itself contains a 13-page Executive Summary giving a high level view of the proposals and recommendations without much of the technical detail.

It is impractical here for me to review the entire document, and indeed this is not really needed because a great deal of the content is a tutorial on hydrogen technology. The report is clearly written by people with more of a background in hydrogen technology and marketing than in railway planning and operations.

Fascinating though this is, the report does not address the most crucial issue of all – what are the implementation scenarios for hydrogen propulsion depending both on technical maturity and on policy decisions still to be made about the evolution of the GO Regional Express Rail (RER) system.

A great deal of confusion lies in the process Metrolinx is following to provision RER. Their intent is to farm the entire thing out to a private consortium:

Design-Build-Finance-Operate-Maintain (DBFOM) Procurement Process

Metrolinx is intending to engage a contractor to upgrade the GO network using a Design-Build-Finance-Operate-Maintain (DBFOM) model. As part of the tender process, bidders will be able to propose both hydrail and overhead wire technology to electrify the GO network. The benefit of this DBFOM approach is it allows one single party to manage all the interrelated decisions necessary and oversee each phase of the process from design to maintenance. This ensures optimal performance is achieved for the entire system, which can create efficiencies. [Website]

However, as the industry now stands, the information needed to allow an informed assessment of technical maturity, feasibility and risk for hydrogen trains at the scale of a GO/RER implementation does not exist. There is a lot of speculation, but it is based on much, much smaller and simpler implementations of various aspects of the technology.

The intent of the proposed study is to acquire as much information and experience as possible so that bidders can bid intelligently. The real challenge will be for this to happen before the Request for Proposals is issued at the end of 2018.

There is a subtle change in the text above to statements by Metrolinx CEO Phil Verster in 2017 when he said that it would be up to bidders to decide which technology they would choose to offer. Instead, the description above states that bidders can propose either technology and it would be up to Metrolinx and the Government of Ontario to decide which version to implement. It is quite likely that for the riskier new technology, bidders will be less willing to accept broad technical risk, and they will charge a premium for this. Whether the government of the day will see any extra costs as worth the investment remains to be seen.

Indeed, although the report states that the Cost:Benefit ratios for conventional and hydrogen options are similar, there is no mention of the risk premium a bidder might place on one option over the other. Moreover, the actual calculation of the ratio is not explained, nor are the total costs given. This raises the question of whether a higher cost is offset by a higher assumed benefit so that the ratios come out similarly, even if the magnitudes of investment differ.

At a recent Board of Trade appearance, Verster was asked about electrification, and replied with praise for Ontario’s “hydrogen economy”. It is quite clear that he drank the Kool-Aid and the government’s usual fascination with technology is getting in the way of his proper role as CEO. Immediately afterward, he reverted to the position that it is up to the would-be builders/operators of the RER network to propose technologies and the risk they are willing to assume.

Later the same day, when asked at a Metrolinx Town Hall about the possibility that hydrogen efforts would delay electrification, Verster replied with the standard response that the vendors will decide. However, the timelines for investigation of hydrogen and the contract award date suggest that a lot of work will be jammed into a very short period, and that Metrolinx’ own technical investigations will overlap the bid process.

A fundamental problem with Metrolinx “benefit cases analysis” (also misleadingly termed “business case analysis”) lies in the calculation of presumed benefits which are built up from a variety of factors. These include not just direct spending, but also the imputed value of effects such as reduced travel times, reduction of congestion and the value of environmental improvements. This side of the analysis is not present in the report, and so it is difficult to ascertain the “benefits” against which each scheme is measured. As for costs, so many elements of the hydrogen train proposal are little more than assumptions about the scalability of existing technology, it is hard to believe that the cost estimate is much beyond the back-of-an-envelope stage.

The capital and operating cost estimates presume a level of certainty about the hydrogen option which simply cannot exist at this point. Indeed, a major purpose of the planned work is to provide the technical basis on which a bidder might construct a proposal. Some capital costs included for conventional electrification are not included in the hydrogen scenario, and there is a wide variation in the range of projected operating costs.

With a planned launch of RER by 2025, the timelines are quite tight because major decisions on the infrastucture needed for either alternative must be made soon so that RER is “ready to roll” when planned.

Notable by their absence are key pieces of information:

  • What is the relationship between the timelines of the proposed hydrogen investigations and prototyping, and the timespan of the DBFOM procurement through all of its phases from initial tender up to revenue service? Can the research phase be completed in time to inform bids from potential builders/operators of the GO/RER network?
  • If the DBFOM bidders depend on investigative work done by Metrolinx or others on its behalf, what liability will Metrolinx have for non-performance if their work turns out to be incomplete or faulty, and therefore prevents the successful execution of the contract?
  • What is or will be the position of the railways, CN and CP, to the presence of hydrogen trains on their systems? Their dislike of electrical distribution and overhead structure in their territory is cited as a benefit of the hydrogen alternative, but one must ask how the railways will view the risks of a new propulsion technology co-existing with their operations.

This brings us to a fundamental question about RER and electrification, regardless of the technology. At the risk of being accused of environmental insensitivity, it must be said that electrification is not a prerequisite for RER implementation at the service levels now planned. Indeed, electrification makes the system design more complex especially where GO services operate over other railways’ territory. The tradeoffs are between many issues including the increased intrusion of more frequent GO service in corridors now hemmed in by residential development rather than by industry. This brings noise and pollution from frequent service with diesel locomotives. Even electric trains are not silent.

Reading between the lines, one might well think that full electrification is now contemplated as something for the future, in the mid 2040s, not in the 2020s. This is fundamentally tied up with questions of implementation and roll out, none of which is addressed in the report because it assumes this is a matter for future study.

Although much discussion reads as if RER will appear overnight in January 2025, Metrolinx plans to begin building up service levels from current to the RER proposal on an incremental basis as infrastructure improvements are completed. This means that a substantial portion of “RER” based on existing technology would exist before electrification, by whatever scheme, actually is “turned on”.

An important part of any implementation plan will include the mechanism by which a DBFOM bidder will take over existing assets, and this necessarily must be spelled out as part of the tender process. This will lead to two huge transitions occurring in parallel: the move from direct Metrolinx capital and operating responsibility for the GO system to a separate provider, and the technology transition from diesel to electric on some or all of the network. Whether Metrolinx has the capability to manage something on this scale, or will simply dump the responsibility in the provider’s lap and hope for the best, remains to be seen.

There is also the fantasy that the “risk” will be transferred from the government to the provider, but that risk comes at a price, and what is effectively “risk insurance” usually has a cap. Examples of capped liabilities, or even of providers walking away from their responsibilities, are not hard to find. Of course there could be problems with conventional electrification too, but they are less likely with a mature technology.

In this article, I will review the recommendations so that readers who want the “short version” can get my opinion without reading all the way to the end. In a separate future article, I will turn to specifics in the detailed report.