Scarborough Subway Update: May 27, 2015

Updated May 30, 2015: The staff presentation is now available online. Some illustrations from it have been included in the article below.

At its May 27, 2015, meeting, the TTC Board received a presentation from Rick Thompson, the Chief Project Manager for the Scarborough Subway Extension (SSE). This presentation is not yet online.

During the presentation, Thompson noted that the process of winnowing down nine alternative routes for the SSE was nearly complete, and that a report on the three short-listed options would be issued fairly soon.

The original nine proposals included two major groups. The first would see the north end of the line continue east from STC on alignments similar to the proposed Scarborough LRT crossing Sheppard at either Markham Road or Progress. Three routes were proposed to reach the existing SRT corridor:

  • Via the SRT as currently constructed.
  • Via Eglinton and Midland, then swinging back into the SRT right-of-way north of Eglinton (this would avoid reconstruction of Kennedy Station on a north-south alignment).
  • Via Eglinton and Midland, joining into the SRT alignment near the existing Midland Station.

The second group takes a north-south alignment through or past STC and all arrive at Sheppard and McCowan as their terminus:

  • A Midland/McCowan option would swing into the Gatineau hydro corridor south of Lawrence to link northeast to McCowan and then follow the McCowan route north.
  • A Brimley option would travel east on Eglinton, north on Brimley and then swing northeast through STC to McCowan.
  • A McCowan option would follow Eglinton to Brimley, then swing north via Danforth Road to McCowan. This was the original proposal approved by Council.
  • A Bellamy option would follow Eglinton to Bellamy, turn north, and then swing back to the northwest to reach the McCowan/STC station.
  • A Markham Road option would follow Eglinton to Markham Road (although the exact alignment east of Bellamy is unclear), then turn north and eventually back west to McCowan. This is the most roundabout of the possible routes.

SSEOptions201505

Events overtook the plans, and a report on the shortlisted options that had gone privately to Councillors made its way into the media. The Star’s Jennifer Pagliaro reported that the three remaing options were the original McCowan alignment, the Bellamy alignment and the Midland route running straight north to meet the SRT corridor.

ci-scarborough-subway-routes-shortlist-web

[Toronto Star, from City of Toronto]

Continue reading

Another Delay For Leslie Street (Updated August 7, 2015)

Updated August 7, 2015 at 6:00 pm: Leslie Street will reopen to traffic using the completed streetcar lanes and the west curb lane on August 8. Work will continue to rebuild the east curb lane and sidewalk.

Updated July 28, 2015 at 12:30 pm: Recent construction photos added.

Updated July 17, 2015 at 2:10 pm: Recent construction photos added.

Updated June 24, 2015 at 5:00 pm: Recent construction photos added.

Updated May 28, 2015 at 2:00 pm: Further information about the design of the track support structure has been added at the end of the article along with historical links.

The seemingly endless work to rebuild Leslie Street south of Queen as the access route to the new Leslie Barns hit another setback with the discovery that a section of track was installed at the wrong elevation. This affects the road profile, drainage patterns and the access to an adjacent condo where residents had expected they would be free of side effects beyond the nuisance of construction.

A surveying error by the contractor, Pomerlau Construction, who have responsibility for the entire Leslie Barns project, caused about 60m of track just north of Eastern Avenue to be installed roughly 9cm above the correct level.

To explain a bit about the structures involved, here are photos from the Leslie Street project.

Continue reading