TTC 2011 Budget Preview — Part II: Capital

In my previous article, I reviewed the TTC’s preliminary information regarding its Operating budget for 2011.  Here I turn to the Capital Budget — the one that pays for major repairs, replacement vehicles and system expansion.

Following this budget from year to year can be challenging.  For the better part of a decade it has been clear that there would be a funding crisis as project deferrals accumulated, and now the dam has finally burst and big-ticket schemes are underway.  The early years of such projects tend to have low cash-flows because they are mainly design work and progress payments on smaller preparatory steps (such as the utility relocations and grade separation on the Sheppard East LRT).  Now, as spending builds on Transit City, the Spadina Subway Extension, replacement subway trains and streetcars, the demand for capital will grow.

During the 2010 Budget Cycle, many projects were deferred beyond 2019 so that they would not appear on the City’s or TTC’s books.  This made the depth of the budgetary hole appear more shallow than it really was.  If that were not bad enough, the TTC has created a new group of projects aimed at Yonge Subway capacity problems and, in the process, is partly pre-judging the outcome of a Downtown Relief Line study.  The combined result is that the funding shortfall shown as $1.344-billion in the 2010 budget papers for the years 2010-2019 has grown substantially, and there is now a funding shortfall of $2.8b for 2011-2020.

The staff budget report does not include a detailed breakdown of the projected funding sources.  Much more information was presented in the September 2009 report in the previous budget cycle.  (Note that the 2009 report does not exactly reflect the budget as it was eventually approved by Council.)

For the 2011-2020 budget planning, the TTC is taking the approach that it should show what spending is required, not just which projects fit within the available envelope.  This puts both Council and various funding agencies on notice about the true scope of future needs.  Council may not like the level of spending, but at least a debate is possible on the relative merit of transit programs.

In theory, this is a welcome change as it avoids the “surprise” factor when unplanned spending requests appear out of thin air.  However, there will be some debate about how critical some “required” projects might be, and what additional projects are still hidden out of sight.

The TTC estimates that restoring previously omitted items as well as new additions will raise the capital requirement by $3-billion over the next ten years.  That is a gross number, but the degree to which it will attract subsidies depends on the generosity and enlightenment of other governments. Continue reading

Multiple Unit CLRV and ALRV Operation

Following up on the comment thread about new Transit City LRVs, John F. Bromley sent along two photos showing MU operation of the “legacy” fleet.

Here is a two-car train consisting of ALRV demonstrator 4900 plus CLRV 4152 eastbound on Kingston Roat at Hannaford on November 28, 1982.  Note the electronic destination sign on the 4900.

This is a six-car train (!) of CLRVs on test at St. Clair Carhouse looking south on Wychwood from Benson on March 21, 1982.  The cars involved are 4191, 4063, 4011, 4095, 4055 and 4186.  Photo by Raymond F. Corley.  (Click on the thumbnail for the larger version which includes the sixth car.)

Note:  I will move all of the comments related to MU operations of the legacy fleet to this post.

More New Streetcars For Toronto (Updated)

Updated on June 15 at 11:30 am:  Thanks to “nfitz” for pointing out that the base prices for both the TTC and Metrolinx cars are available in Bombardier press releases. 

Updated at 11:50 am:  A link to Transit Ottawa’s website has been added.

We gathered at an odd, odd-of-the-way spot — the GO platform at Kennedy Station — a small band of media, government aides and friends of MPPs.  In the background, SRT trains came and went from the upper level of the subway station.

The occasion?  Metrolinx and the Government of Ontario announced Cabinet approval of the extended “Big 5 in 10” project funding and the  purchase of 182 new Light Rail Vehicles for the Transit City network.  The “Big 5” announcement was no surprise — an agency like Metrolinx doesn’t publish a plan like that without knowing approval is certain.  The real news was that Ontario has embraced LRT by actually ordering vehicles.

The irony of the location, a site where we might have seen Toronto’s first LRT line three decades ago, made this event one I just had to attend even if I will have to wait almost a decade to see the new cars rolling out of Kennedy on a rebuilt, extended SRT.

This order builds on the already-approved TTC “legacy” order of 204 LRVs from Bombardier.  That contract included an option for up to 400 additional cars of which 300 were assigned to Metrolinx and the remaining 100 stayed with the TTC.  If Metrolinx wants to bump its order, it has six years to exercise the option for its remaining 118 cars.  This lies well within the timeframe of announcements for another round of LRVs for Toronto or possibly other Ontario systems, but on the timescale of transit planning, is short enough to focus attention on the question “what’s next”.

The new cars (5MB pdf) are slightly longer and wider than the “legacy” LRVs, and the Transit City lines have been designed to match the specs of an “off the shelf” vehicle rather than the more restrictive TTC streetcar system.  A comparison chart shows the major differences between the two new fleets as well as the existing CLRVs and ALRVs.

The contract price is $770-million not including taxes, spare parts and future change orders.  This $4.23-million unit cost compares favourably with the TTC’s $1.2-billion contract for 204 cars (roughly $6-million each), but the actual difference will only be in the range of 5-10% according to Metrolinx CEO Rob Prichard.  Much of the difference lies in the way the TTC and Metrolinx quote pricing and inflation (the TTC’s is an all-in price because as-spent dollars must be quoted in capital budget projections).

The TTC and Metrolinx would do well to present a price reconcilliation so that everyone can make an apples-to-apples comparison.  The last thing we need is a bunch of ill-informed Mayoral candidates presenting the difference as an example of how streetcars are too expensive in Toronto.

Updated June 15:

The base price for each set of vehicles can be found in Bombardier press releasesThe first of the new cars will run on the Sheppard East LRT scheduled to open in 2014.  The remainder of the fleet isn’t needed until 2019/20 when the Finch, Eglinton and (rebuilt/extended) SRT lines are scheduled to open.  This puts much of the order at the back end of the TTC legacy car deliveries running to 2018.  Bombardier and their workers in Thunder Bay are quite happy to see production continuing at their plant.  They have committed to 25% Canadian content, and Bombardier hopes to improve on that figure.

Metrolinx order: 182 cars for $770-million, or $4.23-million each

TTC order: 204 cars for $851-million, or  $4.17-million each

This order sets the technology pattern for other LRT projects in the GTA including Hamilton, Mississauga and Kitchener-Waterloo if any of these progresses beyond the planning stage.  Less clear, however, is the relationship with Ottawa whose LRT scheme recently got back on track with announced 1/3 funding from the federal government.  Siemens was the chosen supplier for the original Ottawa proposal, and will no doubt have a presence in any revival of that scheme.

So begins the long-overdue introduction of LRT to suburban Toronto, although much remains just lines on a plan.  There are the “Phase 2” elements of the four LRT lines, the proposed Sheppard East extension south to University of Toronto Scarborough Campus, the rest of Transit City, and who knows what beyond the 416.  The UTSC extension proposal will be on the Metrolinx Board agenda for its June 29, 2010, meeting, while the remainder awaits the “Investment Strategy” and discussions on how to fund a growing regional network.

A New Carhouse for TTC Streetcars (Update 4)

Updated June 9, 2010 at 7:40 pm:

Council today voted to support the TTC’s proposal for the Ashbridge Carhouse including an access route via Leslie Street.  This was little surprise given that Councillors are loathe to override staff recommendations unless there is an overwhelming case in favour of an alternative.

The first part of the debate turned on whether the carhouse should be at the Ashbridge site at all.  Despite some uninformed grandstanding by would-be mayor Ford, and handwringing by others over what might have been at the Lever site (Sunlight Park) if only its availability had been known sooner in the process, the Ashbridge site selection was approved.

The second part of the debate focussed on the access route.  The TTC argued strongly against the Knox/Russell option and that position won the day, in part because few champions of this route rose in the debate.

The Transit Project Assessment now enters its formal 90-day phase for comment and then goes to the Minister of the Environment for approval.

Continue reading

Sunlight Park Carhouse?

The TTC has a report on its Supplementary Agenda for the June 2 meeting regarding the Unilever property at the foot of Broadview as a possible carhouse site.

During the initial search for new carhouse and maintenance sites, this property was rejected because the then-available acreage was too small.  The situation has now changed, and quite a large block of property is available.  However, the lead time to acquire and clear the site means that a new carhouse and maintenance facility could not be ready in time for the delivery of the Flexity LRV fleet.

All the same, it would be worthwhile investigating this property as a long-term site for a new carhouse replacing Russell and/or Roncesvalles once the high-floor fleet is completely retired.  This would allow redevelopment of two choice pieces of property on Queen Street.

Those familiar with the old Lever Bros. property know it is bordered by Sunlight Park Blvd., a street named after a well-known product.  If this does become a carhouse, that would make a fitting and historical name.

Of course, with that BMW dealership next door, the carhouse would have to feature a large window framing an LRV looking out onto the DVP!

More Toronto Rockets for the TTC

At its meeting on May 6, the TTC approved two add-on orders of Toronto Rocket subway cars.

  • 21 6-car trainsets to replace the H-6 fleet
  • 10 6-car trainsets to provision the Spadina subway extension to Vaughan

The unit cost of the first 21 sets is approximately $15.1-million, while the remaining 10 will cost about $16.3-million each.

These orders will follow the current TR car production at Bombardier’s Thunder Bay plant allowing continuous production at a lower price than if a small Spadina-only order were to be placed closer to the opening date in 2015.

Once these trainsets are delivered, the Yonge-University-Spadina line will operate entirely with TR trains, and the T1 fleet will be shifted to the Bloor-Danforth line.  (The Sheppard line will continue to use T1 equipment that will likely be stored on the YUS, but serviced at Greenwood Carhouse.)

The TTC’s subway fleet plan, presented as part of the 2010-2014 Capital Budget, foresees an eventual fleet of 69 trains on the YUS calculated as follows:

  • Existing service is 48 trains (T1 equivalent)
  • Add 3 for extension of the short-turn operation to Glencairn
  • Add 5 for growth and closer headways with Automated Train Operation (ATO)
  • Add 9 for extension of the short-turn operation to Wilson (when the Vaughan extension opens)
  • Add 1 for growth in each of 2019 and 2020

This gives a total of 67 “T1” equivalent trains.  At this point, the calculation gets a bit murky, but the outcome is roughly the same.  The TTC deducts the extra capacity of the TR trainsets to reduce train requirements by 7, although this very capacity bump is often mentioned as one of the reasons for buying the TRs in the first place.  However, additional effective capacity will be available through the implementation of ATO.

The TTC talks about this in terms of station dwell time, but I believe this is a red herring.  Passenger loading times have nothing to do with ATO.  What will be possible, however, is for trains to operate at a higher speed on those parts of the line where stations are further apart, and this will not require complete re-engineering of the signal system as would have been the case for the existing block signals.  Faster trips mean that the same number of trains can operate on a shorter headway and, thereby, increase capacity.

After allowing for spares at 13%, the total fleet requirement is 69 trainsets and this is the combined size of the three TR orders now on the books.

LRV Design Turns to the Public

The TTC has launched a new website devoted to the design of the new Toronto streetcars.  The video on the opening page is a bit cheezy, but the basic idea of the site is to solicit feedback from people about these cars.

I am sitting on a review panel for this process, and in our first meeting the common thread was that we all wanted to talk about more detail than was on offer.  It will be interesting to see what the general feedback is, and how much of it is reflected in the final design.

Meanwhile, Long Branch riders take note:  the graphic for this consultation shows a car signed “501 Long Branch”.  You will get new cars eventually, although they may not show up very often.

Queen’s Park Commits to Transit City, Sort Of

Queen’s Park has announced that it will build the four previously funded Transit City lines (Sheppard East, Finch West, Eglinton and the SRT rebuild/extension) as well as the VIVA busway, but over a longer time than planned.

Tess Kalinowski writes about this in today’s Star.

The construction start dates will be adjusted:

  • Sheppard and VIVA are already underway and will continue.
  • Eglinton will not start until 2012 rather than the originally planned 2010
  • Finch West will not start until 2013 rather than 2010
  • The SRT will continue operating until after the Pan Am Games in 2015 at which point it will close for reconstruction.  Second-hand Mark I ICTS cars will be purchased from Vancouver to supplement the existing fleet in the interim.

Also rumoured is a Metrolinx announcement regarding purchase of cars for these lines from Bombardier.

All of the details will come out at the Metrolinx Board meeting on May 19, 2010.

The City of Toronto has proposed that it would finance the projects starting on the original schedule as this would be cheaper than other capital expenses it would have to undertake (a larger bus fleet and a new garage) to handle system growth pending opening of the Transit City lines.  One might argue that they should just “get by” if this would only be a short-term pressure, but if Queen’s Park’s new promise falls through (there might be a different party in power by the time in came to actually pay up), the TTC would be seriously behind in providing capacity.

Rob Prichard of Metrolinx argues that the financial goal is to minimize provincial debt, and starting the projects early would add to the debt regardless of who pays the interest costs in the short term.  This is really the nub of the debate.  Queen’s Park seeks to minimize its book debt, and must deal with accounting standards that no longer allow governments to hide debt through leases or third-party financing.  Oddly enough, this also affects some privatization schemes because, ultimately, the government is still on the hook to pay for the lines.

There are much larger questions in play here.

Metrolinx “Big Move” plan includes over 50 projects, and we have no idea of how Queen’s Park will pay for them, much less operate the network once it is built.  If the first five projects are stretched over the next decade, when will work begin on the others?  Will any new revenues (tolls, taxes, the Tooth Fairy) be used to fund additional projects, or will they backfill the original five?

Metrolinx’ mandate for a financial plan was explicitly set up to keep funding issues off the radar until after the 2011 provincial election, but that idea (a triumph of politics over good planning) fell apart when the 2010 budget cut funding for transit.

On top of this, there is no word on a provincial role in funding operating costs of local transit systems.  In a best-case scenario, this might show up in the 2011 budget as a pre-election goodie, but Toronto and the TTC will go into their own budget cycle (which is largely complete by the time Queen’s Park announces its own plans) facing a TTC operating subsidy of about half a billion dollars.  Mayoral candidates have a lot to be worried about, and they won’t solve the problem by counting the pencils.

Transit City Cars to be Built by Bombardier

Today, Metrolinx announced that they would exercise the option in the TTC’s order for Light Rail Vehicles with Bombardier for the Transit City fleet.

Here is the press release:

Metrolinx will be entering into formal negotiations with Bombardier Inc. to exercise the option from the replacement streetcar contract to purchase Light Rail Vehicles (LRVs).

The negotiations with Bombardier to procure LRVs are part of Metrolinx’s phased plan which is being developed for the four Light Rail Transit (LRT) projects as requested by the Province.

In June, 2009, following an open competitive procurement process, Bombardier was awarded the original contract to produce vehicles for TTC’s legacy streetcar replacement. This contract contains an option clause that provides Metrolinx with the ability to purchase additional LRVs from Bombardier for the four LRT projects.

Over the past six months, Metrolinx, with the assistance of the TTC and the international transit car expert LTK Engineering Services, evaluated its procurement alternatives. Metrolinx, with the unanimous support of its Board of Directors, concluded that entering the negotiation to exercise the option would obtain the best value for Ontario.

If the negotiations are successful, Metrolinx will announce the details of the procurement when an agreement is reached.

Note the reference to the “phased plan”.  This is the stretched out implementation scheme for the funded Transit City lines contemplated by the March budget cuts to transit.

The timing of this announcement is odd in that it falls between Metrolinx Board Meeting cycles.  It’s almost as if Queen’s Park is trying to tell us that they have not forgotten Transit City.

Updated at 10:15 pm:  See also coverage by the Toronto Star’s and National Post of this announcement.

Open Houses: Ashbridge’s Bay Carhouse & Scarborough LRT

Two upcoming open houses may be of interest to readers.

Ashbridge’s Bay Carhouse

April 8, 2010 from 6:30pm to 9:00pm at the Toronto EMS and Fire Academy, 895 Eastern Avenue

The project website includes notes from previous public sessions and a map of proposed alternative routes to the carhouse from the existing streetcar network.

The notice for this meeting also includes reference to information about the new streetcars.  The final design for these cars is not yet determined, and an advisory committee (of which I will be a member) is now being organized by the TTC to assist with this.

Scarborough RT to LRT Conversion

Two public meetings have been scheduled for the Scarborough LRT conversion project.  This is the official launch of the Transit Project Assessment (TPA).

April 12, 2010 from 6:30pm to 9:00pm at Jean Vanier Catholic Secondary School (Cafeteria), 959 Midland Avenue (north of Eglinton)

April 15, 2010 from 6:30pm to 9:00pm at the Chinese Cultural Centre, 5183 Sheppard Avenue East (at Progress Ave)