TTC’s Five Year Plan Reviewed

TTC CEO Andy Byford was hired by former chief Gary Webster to modernize management practices and provide focus to an organization that had lost its way.  Thanks to Webster’s ousting at the hands of the subway-loving, LRT-hating Mayor Ford, Byford unexpectedly found himself top dog.  After a year in Toronto, Byford released his five year corporate plan on May 29, 2013.

Those of use who follow the TTC closely have heard a lot about this plan as a centrepiece for the future of our transit system.  Byford’s talks at meetings around the city, most recently a Town Hall presented by Councillor Josh Matlow on the eve of the plan’s release, raised expectations for a major document, a fundamental shift in how the TTC would operate.  If this were a summer movie release, Byford’s appearances would be the equivalent of ever more tantalizing trailers and “sneak peeks” at what would come.

The plan’s release was something of an anti-climax — a press release via web and email, no additional information, no political feedback to indicate support.  The TTC board discussed the plan in its private session at their May 24 meeting, but made no public comment.  Internally, the plan was launched at staff meetings that will continue over coming weeks to reach throughout the 12,000-strong company.

Media attention is, to be generous, muted with the story completely submerged under the Ford follies at City Hall and the Metrolinx Investment Strategy.

Continue reading

TTC Meeting May 24, 2013 (Update 3)

The agenda for the TTC meeting on May 24 contains a few items of interest, but also a troubling sign that matters of public interest are being debated behind closed doors.

Items included in this preview:

Updated May 23 at 12:10 am:

Links to the TTC construction pages for the York Street, Ossington Avenue and Kingston Road reconstruction projects have been added.

A reference to a statement about the New Streetcar Implementation Plan attributed to Andy Byford at the April Commission meeting has been corrected to reflect that it was made by Chris Upfold, Chief Customer Officer, who was standing in for Byford at that meeting.  TTC’s Brad Ross has confirmed that this plan will be presented in the public session of the June Commission meeting.

Updated May 23 at 9:15 pm:

The Kingston Road construction project info has been updated to reflect the early replacement of streetcars by buses effective June 3.

Updated May 25 at 1:30 pm:

This article has been updated to reflect events at the Commission meeting.

Continue reading

Five Years, Seven Goals: Where Will The TTC Be In 2018

TTC CEO Andy Byford addressed the Empire Club on May 13, 2013 setting out a strong argument for political and financial support for the transit system (full text at the Torontoist site).  After last week’s debacle at Council where almost nobody took any sense of responsibility for the future of transit beyond their own doorsteps, arguing for the TTC is a hard battle.

On one hand, we have an intensely local debate at the ward, if not the neighbourhood level, with the worst of petulant “I-want-a-subway-too” politics.

On the other, the region and the province are preoccupied with funding a large-scale plan that happens to have a spin-off for local transit, but one that will only give Toronto a fraction of what it costs to run and maintain the TTC today, let alone make substantive improvements.

In some ways, the TTC has been its own worst enemy managing on one hand to alienate potential supporters with poor community relations, unreliable budgeting and declining service quality, but on the other managing to attract riders and be more financially “efficient” in spite of itself.  When political support for better funding and service is needed, the “success story” is that the TTC has managed to cram more riders into fewer buses and streetcars.

This is not a sustainable approach to transit.  Growth – which has come disproportionately in off-peak periods when there is still some capacity in parts of the system – cannot continue on this basis.

Byford will formally launch a Five Year Plan for the TTC in the week of May 27, 2013, but his speech gives a broad outline of his goals.  Are they enough, or is there too much concentration on the decor while the house rots around us?

Continue reading

TTC Meeting Wrapup: April 24, 2013 (Updated)

The TTC met on April 24 to discuss a rather thin agenda, and the meeting was over in a not-quite-record 90 minutes.  Discussed here:

  • May meeting preview
  • CEO’s Report
  • Customer Satisfaction Survey
  • Property Acquisition Management Plan
  • Pape Station reconstruction
  • A deputation about the 507/501 streetcar service

Updated May 6, 2013 at 5:20pm:  In the original version of these notes, Commissioner Heisey’s concern about unreliable service on Dundas Street was reported.  The Commissioner has written to me to note that the service was actually worse than how I quoted his remarks.  His correction is included near the end of the “Customer Satisfaction Survey” section below.

Continue reading

How Bad Is TTC Service: A First Quarter Report

Among the TTC’s many promises under its Customer Charter is the provision of quarterly stats on the reliability of each of its surface routes.  This information recently went online on the TTC’s website, although you have to dig to find it.

The path is from Customer Service on the top navbar, then to Customer Charter on the side bar, then to Quarterly reports, and finally scroll down.  Or you can just click here.

This table covers the first three months of 2013, and lists the reliability of every surface route.  “Reliability” is defined roughly as:

  • If the distance between a vehicle “B” and the one preceding it “A” is within three minutes of the scheduled headway, then the vehicle is within the acceptable window of reliability.
  • The measure is taken at various points along a route (we don’t know the locations or number for any route), and summed across an entire quarter’s operation.  This will smooth out everything but very large scale, long-lasting disruptions, and will tend to give an index that tracks the overall behaviour of the route.

The system-wide target for streetcar routes is 70% punctuality (within the headway window), and for buses it is only 65%.  Looking at individual routes, there are huge discrepancies.

No route gets over the 90% line, although several are in the mid to upper 80s.

  • 8 Broadview
  • 31 Greenwood
  • 44 Kipling South
  • 78 St. Andrew’s
  • 510 Spadina

Of these routes, four are relatively short bus routes where congestion is not an issue, and with only a modicum of effort, operators should be able to stay on time.  The Spadina car is a special case because it runs with a very short scheduled headway for much of the day, every day of the week.  It is physically difficult for cars go get more than (H + 3) minutes apart, and impossible for (H – 3) because this would be a negative number.  Service that meets the target is very easy to achieve even if the line appears chaotic at times simply because there are so many vehicles close together.

Continue reading

TTC Meeting Wrapup: March 27, 2013

The Toronto Transit Commission met on March 27.  This wrapup includes comments on:

  • Purchase of Articulated Buses
  • The CEO’s Report for March 2013
  • The Gateway Newsstand Contract
  • Priorities for Subway Station Elevators

The Leslie Barns project, and the streetcar system renewal in general, received comments in the press recently about the scale of expenditures, and the sense that the TTC estimates understated the full cost.  See the National Post here and here.  I will discuss these issues in a separate article.

Updated April 2, 2013:  Rahul Gupta has addition background on the Gateway issue at InsideToronto.com.

Continue reading

Saying “Sorry” Is Only The Beginning

TTC CEO Andy Byford’s Youtube apology for subway service fiascos on March 18 stirred a lot of interest, along with an interview on CBC’s Metro Morning.  This will no doubt continue at a town hall meeting tonight (which I cannot attend due to scheduling conflicts).

Monday afternoon’s peak was not a good one for TTC subway service:

  • 5:16 Trains holding for smoke at track level at Eglinton Station (cleared 5:31)
  • 5:25 Trains holding for smoke at track level at Keele Station (cleared 5:33)
  • 5:58 Power cut at Dupont halting service from St. George to St. Clair West.  Train doors opened in the tunnel.  24 minute delay

The times shown for the smoke delays are from timestamps on TTC e-Alerts, and the actual duration of the delay was probably longer.  We know from Byford’s comments that there were a few passenger assistance alarms from people requiring medical assistance, but these never showed up as official alerts to riders.

The TTC’s daily measurement of service punctuality for the Yonge line fell to 93%, below the target of 96%.  This is an all-day average of performance at many places on the line, and it takes a big upheaval in service to make a dent in the considerable amount of more-or-less punctual service rating for the line as a whole.  The index has never been known to fall below 90%.

The delays were only part of the regular menu of service disruptions including mechanical failures of trains, track and signal problems, weather, security incidents, not to mention suicides.  Running a well-behaved service can be quite challenging.  One of those challenges is to simply keep people informed about what is going on when multiple delays interact to foul up service, and info about what is left running changes from moment to moment.

Seeing Andy Byford there on YouTube with his mea culpa is a nice touch, but there is a limit to how many of these the TTC can issue before riders simply say “oh no, not again”.  The TTC’s new Customer Charter commits the organization to improvement, but the message coming through loud and clear at public meetings is “show me”.

Monday’s events highlight some obvious issues for managing complex events, but they also raise questions about how much we can reasonably expect of the transit system.

The incident with the doors opening on a train between stations was a matter of human error by the Guard who inexplicably opened them when the train was stopped north of Dupont Station at a red signal.  Automatic Train Control could have prevented this, but that’s years away and, fortunately, this sort of incident is extremely rare.  The TRs will only open their doors when the train is stopped, and indeed the sensing associated with this feature is part of the extra delay time when trains arrive at stations.

Updated Mar 21:

There has been another incident of train staff accidentally opening doors in the tunnel as reported today by the CBC.

Any incident like this, and including fires or smoke, requires a power cut and affects service in both directions, whereas an ill passenger, most of the time, holds up service only one way for a brief time while they are assisted off of the train.

However, there are a lot of incidents, and each of them adds to discontent among the affected riders.  Even if someone only encounters a major delay once or twice a month, that’s the experience they remember and tell their friends about.  What’s more, if the system cannot get through the rush hour without, simply as a matter of probabilities, having a few non-trivial delays, this compromises the TTC’s ability to achieve its planned capacity.

A few years ago, the TTC had an independent review by UK-based transport consultants who found that, generally speaking, the TTC subway wasn’t all that bad for systems of comparable age and technology.  However, the consultants warned that hoped for increase in capacity required more reliability in trains and infrastructure, fewer incidents of passenger illness caused by crowding, and a general attention to running as tight an operation as possible.  Some delays are inevitable, and for them the issues are incident management, good communications with passengers, provision of alternate service if possible, and quick recovery of full subway capacity.

When we talk about how close the TTC might be to running out of capacity, optimists love to quote the highest possible figures — automated trains running on the closest headways, passengers flowing quickly to and from trains to minimize dwell times, equipment with superb reliability, and a magic world in which nothing ever goes wrong.  That’s not how the subway actually operates, and Byford’s task is to expunge every source of “controllable delay” from the system.

On Metro Morning, Byford made a passing remark about improving terminal operations and getting trains out promptly.  That’s an important change, one that is essential to maximizing the trains/hour actually operated and maintaining good service spacing.

Getting the subway to work as well as it possibly can is an important start, but it’s only part of the job.  We will probably never see YouTube apologies for the large gaps in service on surface routes, but instead will have small tutorials on why short-turns are required.  Sadly, “TTC Culture” still includes too strong a sense that most of the problems are external and this must change.

A target of 65% for “punctual service”, itself based on a generous 6-minute-wide margin for service relative to scheduled headway, accepts that the odds are better than half that a rider will encounter a significant gap at least once a day, probably more if they take multiple trips.  What we don’t see is a measure of how well or poorly passenger loads are distributed among buses and streetcars, and what the riders see rather than what the hourly or daily averages report.

If transit really is going to attract more riders, especially those facing longer trips, reliability is key.  To some, the solution is a network of subways, but that simply won’t happen thanks to cost and the time needed to build them.  Some new rapid transit capacity is overdue, but it must be placed where it will do the most good, not as pet projects of particularly noisy and influential members of Council.

Meanwhile, the TTC must address service quality on that vast part of the network not served by subways, and Andy Byford must be just as prepared to take responsibility for the Finch and Dufferin buses and the Queen streetcar as he is for the Yonge subway.

Analysis of 29 Dufferin for March 2012 — Part II: Running Times (Updated)

In Part I of this series, I reviewed problems with headway reliability on the 29 Dufferin route.  An issue commonly raised by operators is that there are times when schedules do not provide enough time for vehicles to make their journey, and this results in a variety of problems including irregular service.

In Part II, I turn to the actual time required for buses to make their journey on the route during the month of March 2012.

Updated March 20, 2013: In the comment thread, there was a question about whether different vehicles operating on this route showed any difference in travel times.  I have added a section to the end of the article to address this.  (The short answer is “no”.)

Continue reading

Past and Future Streetcar Service Capacity

Now that the first Low Floor Light Rail Vehicle (LFLRV) is rolling through Toronto streets on test runs, the question of service quality and capacity for streetcar routes is once again an issue.

The most recent TTC document setting out their intended use of the new fleet appeared in the 2013 Capital Budget Blue Books.  These are not available online, but I presented the TTC’s fleet plan in an article last fall.  From the numbers of vehicles to be assigned to each route, one can work back to the service frequency and capacity numbers.  In general, peak period headways get a bit wider, but the capacity goes up, in some cases dramatically.

The TTC faces two challenges: one on the budget, and one in operations.

Toronto Council has been extremely stingy with operating subsidies and “flat lined” the TTC over the past two budget cycles.  Hard liners will want the TTC to simply replace service on an equivalent capacity basis and maximize the savings in operator costs.  This would be a disaster for service quality even if the TTC actually ran cars on the headways they advertise.

On the operational side, any increase in headways brings even wider gaps when the service is upset by weather, random delays and short turns.  It is already a matter of record that the largest drop in riding over the past two decades came on the lines where 50-foot long CLRVs (the standard Toronto cars) were replaced by 75-foot long ALRVs (the articulated version) on an equivalent capacity basis.  Falling riding led to reduced service and the familiar downward spiral.  This must not happen when the new fleet rolls out across the system.

Since at least the mid-1990s, the TTC has told us that they cannot improve streetcar service because they have no spare cars.  In part, they are the victims of their own fleet planning.  The TTC originally rebuilt some of its old PCC cars (the fleet preceding the current one) in order to have enough to expand operations on the Harbourfront and Spadina lines.  However, by the mid-1990s, service cuts on many routes thanks to the economic downturn in that decade and the subsidy cuts by the Harris government, reduced the fleet requirements to the point where the PCCs could be retired and the Spadina line opened without buying any new cars.  When riding started to grow again, the TTC had no spare vehicles to improve service, and to make matters worse, the fleet was entering a period of lower reliability thanks, in part, to poor design.

Toronto waited a long time for new cars to be ordered, and this process was delayed both by the decision to go with all low-floor cars, and by political meddling at City Hall.  New residential construction along the streetcar lines pushes up demand, but the TTC cannot respond with better service until they have more cars.

Recent discussions about the new cars have included comments about how we cannot possibly have more streetcars on the road.  What many people forget is that the streetcar services were once much better than today.  In this article, I will look back at service levels once operated in Toronto, and at the service that we might see if the TTC actually operates the new fleet in the manner their Fleet Plan claims.

Continue reading