Subway Restricted Speed Zones

At its meeting of September 24, 2024, the TTC Board received a presentation from Fort Monaco, Chief Operations and Infrastructure Officer, on subway restricted speed zones (aka “RSZs”).

From the sheer number and duration of these, it has been clear to riders that the TTC fell behind both in the quality of its track maintenance, and in its ability to work through the backlog. It is one thing to say that RSZs are implemented for safety, but when they are so numerous, “safety” had become a matter of necessity beyond routine levels.

The current RSZ map, together with expected dates when these zones will be repaired, is from the appendix of the presentation deck. Monaco noted that with each RSZ adding about two minutes of travel time, the trip from Wilson to Union Station is extended by about 15 minutes.

The locations where these occur are overwhelmingly in “open cut” locations where rail is laid on ties and ballast. In tunnels, rail is either mounted directly on the concrete tunnel floor, or on structures which themself are fixed to the tunnel. Such track cannot shift around as much from forces of passing trains. Other track issues include several types of wear that can induce noise and rough train operation, but also fractures from metal fatigue.

Since January 2023 the accumulated count of RSZs is almost 300. Of these, only 30 were planned, typically for track renewal projects where a slow order is required over an extended period while work is in progress.