Broadview Station Loop Expansion Deferred

The planned expansion of Broadview Station Loop to allow two streetcars to occupy the 505 Dundas loading bay at a time has been deferred to an unspecified later date.

At the TTC Board meeting on June 12, CEO Rick Leary said that there would be a new operating procedure at the loop where streetcars would not lay over, although just how this will be achieved is difficult to understand. A common requirement at terminals is for operators to have a short “nature break”, and this is really not something that can be eliminated by managerial fiat.

A related problem is that schedules generally have excessive running time to avoid the need for short turns. If cars do not take layovers at terminals they will make even slower trips across their routes than they do today. On King and Dundas, they have the option of putting all of the layover time at their western terminals.

The TTC has an astounding ability to make streetcar service slower and less reliable, and this has become so ingrained it is hard to see any improvement in the near future.

Operational details of the change have yet to be announced, and in any event we will not see the effect until 2024 when streetcars finally return to Broadview Station.

Track work at the station planned for June 2023 will now address the on-street track on Broadview and Erindale while the loop will wait for another day when and if it is expanded.