Toronto Council Pursues Details of Metrolinx Projects

An ongoing problem for anyone attempting to work with Metrolinx on their projects is the lack of transparency, the fog through which details emerge, if at all, on what they actually propose to do.

Distrust of Metrolinx to deal fairly and honestly with communities and their political representatives led to widely-supported motions when Council considered two reports regarding Metrolinx projects on October 1, 2020:

Included here are Council motions regarding:

Also included are recent replies to queries from me about the Ontario Line.

Continue reading

Drifting Timelines on Metrolinx Projects (Fall 2020 Update) (Revised)

Back in June 2020, I wrote about the gradual drift in the planned dates for various Metrolinx projects as reported by Infrastructure Ontario [IO for short].

See: Drifting Timelines on Metrolinx Projects

The September 2020 Market Update has been issued by IO and it shows changes in some projects from the June update.

Sept 26, 2020: Revised to include the change in financing method for the OnCorr GO Corridor project.

Is The P3 Model Falling Apart?

Two revisions in the large GO project procurement model involve a change from private sector financing to traditional government borrowing.

This suggests that the market willingness to finance projects on behalf of the government, or at least to do so at rates competitive with direct government borrowing, may be on the wane. That implies that the “P3” model may be coming unglued.

At its heart, this was always seen as an accounting mechanism to shift debt off of the government’s books, and without this shell game, a major argument for P3s could vanish.

The Future of Electrification

The change in financing model could shift any decision on propulsion technology back to the government.

Metrolinx had pushed this off its plate by saying that the bidders who were going to design and operate a future GO network would make that choice. This punted the knotty political problem of hydrogen trains touted former Premier McGuinty out of Metrolinx itself.

Will Ontario be willing to finance the large up-front capital costs of electrification itself with so many other pressures on financial resources, or is electrification about to fall out of consideration while spending focuses on service expansion?

Ontario Line

The project is in three sections of which the last will be the “Northern Civil, Stations and Tunnel” which includes the portion of the line east of the Don River and north to Eglinton, but not the Maintenance Facility which is included with the “South Civil” portion as it is needed relatively early in the project.

Some of the work on the North section between the Don River and Gerrard Station might be undertaken as part of the GO Corridor improvements, but exactly what this might entail has not been made public.

Since the last update, there are three changes for the North section:

  • The date for RFQ (Request for Qualifications) issue has been changed from Winter to Spring 2022.
  • The RFP (Request for Proposals) issue has been changed from Spring 2022 to Fall 2022.
  • The Financial Close (in effect, the contract signing) has been changed from Fall 2023 to Spring 2024.

The remaining portions of the line are on the same timeline as before.

The timelines for this project, with financial close for the first two portions in fall 2022 and for the third in spring 2024 puts this beyond the next provincial election expected in mid 2022, the four-year anniversary of the Ford government’s election. Who will be in place to make final decisions, and what the government’s financial position will be by then, remain to be seen.

Line 2 East Extension (Scarborough Subway)

This project is now shown with two portions: one for the tunnel, and the other for the stations, railway and systems.

There is no change in the tunnel portion of the project, but the remaining portion has reverted to the dates shown for the overall project in the Winter 2020 update.

GO Expansion Lakeshore West Corridor

The financial close for this project has been changed from Winter 2021 to Spring 2021.

GO Expansion Lakeshore East-West Corridor

This was originally to have been a “Build-Finance” project, but it is now “Design-Bid-Build”, a change that was made in August 2020 according to the IO report.

GO OnCorr Projects

[Added to this article on September 26, 2020]

This is a very large project including future operation of GO Transit and possible changes in the propulsion technology.

The procurement model has been changed from “DBOFM” (Design-Build-Operate-Finance-Maintain) to “DBOM”. The proponent will no longer finance the project which has a projected value of over $10 billion.

All other projects are unchanged. A summary of the Metrolinx projects tracking their changing status is available in this spreadsheet (revised version).

Ontario Line Draft Environmental Conditions Report Released

October 6, 2020: This article has been updated with information on the north section of the Ontario Line between Danforth and Eglinton (Pape to Science Centre).

September 29, 2020: This article has been updated with information on the east section of the Ontario Line between the Don River and Danforth.

September 23, 2020: This article has been updated with information on the central section of the Ontario Line between Osgoode Station and the west side of the Don River.

I asked Metrolinx a series of questions about information released in the two “neighbourhood updates”:

1. The station boxes that are shown are barely 100m long. What provision will the stations include for ventilation shafts? Will they be within the platform area or will they be beyond the end of the platforms as on, for example, the Crosstown line?

2. There is only minimal discussion of entrance locations. Will the stations include two separate paths from platform to surface as per fire code?

3. Will there be emergency service buildings between the more widely spaced stations to provide egress in case of a tunnel fire?

4. There is reference to using the space for lower Queen station as part of the design, but this area is (a) fairly small and (b) already used for a variety of purposes. Is the intent to have the OL go beneath all of the existing structure with the actual track and platform below lower Queen and with the “ghost” station space (which is already used in part as a pedestrian underpass between northbound and southbound platforms) only used for circulation space between the two lines? That would make a lot more sense than actually trying to take OL trains through the existing lower Queen Station.

5. The diagram of the Don Yard shows a direct conflict between the structure for the westbound OL portal and the Richmond Hill GO corridor. What is happening here?

In response, Metrolinx issued the following rather opaque reply:

Metrolinx will factor in all necessary safety and accessibility requirements into the Ontario Line designs. The most recent update is a more detailed vision of the project, but more details are still to come.

Metrolinx will be closely coordinating any Ontario Line work alongside our existing rail operations to minimize or avoid service impacts, while also respecting concurrent GO Expansion work.

Email from Scott Money, Metrolinx Media Relations

The original article begins here:

On September 17, 2020, Metrolinx released the Draft Environmental Conditions Report [Draft ECR] for the Ontario Line.

A huge volume of material is included, thousands of pages, but the vast majority of this only documents existing conditions and gives little indication of the actual “environmental impact” that building and operating the Ontario Line will have.

For convenience, here are links to source materials. The Draft ECR link leads to a page with many documents, some of which are very large PDFs.

Jump to section-specific discussions:

It is self-evident that the actual impact of any project cannot be known without the details of what will be built. This information is not yet public and only sample area maps which are drafts “for illustrative purposes only” have been released for a portion of the route. More will follow in coming weeks, but one must ask why they are not all available now if Metrolinx expects informed comment on their proposal.

Even on the supplied maps, many key features are missing including:

  • Vertical and horizontal alignment including property requirements for construction
  • Station sites, access and circulation plans including redundant paths between platforms and the surface for fire safety
  • Emergency service buildings and access structures to tunnels
  • Utility buildings such as substations

During the public consultation process and as recently as the April 2020 report summarizing this work, the project timeline was illustrated as below. This clearly shows that only one set of “Environmental Reports” were to be published and this was expected in Fall 2020, that is to say, now.

Source: Engagement Summary Report, April 2020, p. 43

Ontario changed the legislation relating to Environmental Assessments with the effect that the item of most interest — the actual design and effect of the project — will not be known until later in the process than the public originally expected.

As required under O. Reg. 341/20, Metrolinx is preparing an environmental conditions report, which will be published for public review and input prior to finalization. The report will characterize the environmental setting in the vicinity of the Ontario Line, including existing noise and vibration levels, air quality, natural environment features, built heritage and archaeological resources, socio-economic and land use features, and traffic conditions.

Metrolinx is also planning to publish early works reports for components of the Ontario Line project that are planned to proceed to implementation ahead of completion of the Ontario Line assessment process.The early works reports will assess the environmental impacts of the early works and describe associated mitigation measures. The early works reports will be published for public review and input prior to finalization.

Following finalization of early works reports, Metrolinx will publish an environmental impact assessment report, which will assess the environmental impacts of the Ontario Line and describe associated mitigation measures. The environmental impact assessment report will be published for public review and input prior to finalization,as part of Metrolinx’s effort to meet the best practices and community consultation principles that are part of the Environmental Assessment Act with all projects. This will be followed by early works reports and the Environmental Impact Assessment Report environmental impact evaluation results, mitigation measures, monitoring activities, potentially required permits and approvals and other components.

Source: Metrolinx Update to City of Toronto, p. 13

There are now three streams of reports and consultation. First up is the ECR which has just been issued, but separately there are reports on “Early Works” (design and construction that can get underway to advance the project before the full design is locked down) and then the “Environmental Impact Assessment Report”. It is only in the last report that the details of design and effects on neighbourhoods will be revealed, and this is planned for winter-spring 2021.

Source: Ontario Line Environment Page

On a parallel track, the procurement process is already underway with teams short-listed to bid on two major contracts:

  • Rolling Stock, Systems, Operations and Maintenance (RSSOM)
  • Southern Civil, Stations and Tunnel (Exhibition to Don Yard Portal)

The Northern Civil, Stations and Tunnel package (Don Yard Portal to Eglinton) will be tendered separately in 2022.

The ECR contains material reviewing conditions in a wide study area shown in the map below.

The study area is relatively wide in some areas, but narrower in others implying that a range of options was reviewed for parts of the route. Notable by its absence is the original Eastern-Pape corridor for the Relief Line showing that there was never any intention of entertaining this as an option, if only for comparative purposes.

The study area in Thorncliffe/Flemingdon is fairly large in part because this includes the proposed maintenance yard, but also because alternative routes through this area were under consideration.

Source: Draft Environmental Conditions Report, page i

Alignment plans are shown only for the western segment between Exhibition and Queen/Spadina at this point. Metrolinx plans to unveil details of additional segments on a weekly basis for other parts of the line:

  • Osgoode Station to Don Yard
  • East Harbour to Pape South
  • Pape North to Science Centre (Eglinton)

They have published details for the first segment in a blog article as well as on the West Neighbourhood page (both linked above). I will update this article as information on these segments is revealed.

One burning issue in the third segment is the alignment through and effects on the South Riverdale and Leslieville area between East Harbour and Gerrard Stations. Although details on this have not been published, there is a note in a recent Metrolinx report to City Council (linked above) about the area just north of Queen Street where a recreation centre stood in the line’s path.

The Ontario Line team is working with City staff to ensure the project is delivered with minimal impacts to sensitive community areas and properties, such as parks and community centres. For example, following significant design and engineering effort, the station at Riverside/Leslieville has been positioned to avoid impacting Jimmie Simpson Community Centre. Efforts are underway to minimize impacts to other key community assets, including, Pape Avenue Middle School, Valley Park Middle School, Bruce Mackey Park, the future Ordnance Park, places of worship and other locations. Where an impact cannot be avoided the team will continue to work with City staff to address continuity of programming.

Source: Metrolinx Update to City of Toronto, p. 13
Continue reading

Drifting Timelines on Metrolinx Projects (Updated)

Updated June 23, 2020 at 1:50 pm: The table of projects has been updated to include anticipated events, notably “financial close” dates, that were included in various project announcements by Infrastructure Ontario. Also Union Station Platform Expansion was described in the original version of this article as closing sooner than originally projected. This has been corrected to show a delay of roughly nine months.

Infrastructure Ontario recently released its Spring 2020 Update for P3 projects under its control including several Metrolinx projects. To date there have been three of these updates:

These updates include information on the project status, the type of procurement model, and the expected progress of each project through the procurement process. This provides “one stop shopping” compared to Metrolinx’ own site. As a convenience to readers, I have consolidated the three updates as they relate to transit projects to allow easy comparison between versions.

Some projects have evolved since the first version, and in particular the delivery dates for a few projects have moved further into the future. The “financial close” dates for some projects, in effect the point at which a contract is signed and real work can begin, has moved beyond the date of the next Provincial election. Whatever government is in power after summer 2022 will have a final say on whether these projects go ahead.

Subway Projects

Ontario Line

The Ontario Line was previously reported as a single project with a price tag of over $10 billion. In the Fall 2019 update, the intent was to have the financial close in Winter/Spring 2022 ahead of the election. In the Winter 2020 update, this changed to Spring 2022.

In the Spring 2020 update, the project has been split into separate parts to reflect industry feedback about the original scope.

  1. GO Corridor from Don River to Gerrard
  2. South Tunnels, Civil Works and Stations CNE to Don River
  3. Rolling Stock, System Operations & Maintenance
  4. North Tunnels, Civil Works and Stations

The GO corridor work will be done as a conventional procurement by Metrolinx and will be bundled with upgrades to GO Transit trackage.

The financial close for items 2 and 3 above is now Fall 2022, and for item 4 it is Fall 2023.

This means that an actual sign-on-the-dotted-line commitment to the project will not be within the current government’s mandate. Even the so-called “early works” comprising the southern portion of the route from Exhibition to the Don River is not scheduled to close until Fall 2022. The northern portion, from Gerrard to Eglinton will close in Fall 2023. This contract is being held back pending results for the south contract to determine the industry’s appetite for the work.

The southern portion, with a long tunnel through downtown and stations in congested street locations would start first. However, the line cannot actually open without the northern portion because this provides the link to the maintenance facility which is included as part of item 3 above although the actual access connection would be built as part of item 4.

An issue linking all of these projects is the choice of technology which, in turn drives decisions such as tunnel and station sizes, power supply, signalling and maintenance facility design. When the Ontario Line was a single project, Metrolinx could say that this choice was up to the bidders, but now there must be some co-ordination to ensure that what is built can actually be used to operate the selected technology. It is hardly a secret that Metrolinx is promoting a SkyTrain like technology, although which propulsion scheme (LIM vs rotary motors) is not clear. There are well-known problems with LIMs and the power pickup technology used on the SRT, and this would also be a consideration for the outdoor portions of the Ontario Line.

Scarborough Subway Extension

Like the Ontario Line, the Scarborough Extension has been split into two pieces. The first will be the tunnel contract from Kennedy Station to McCowan. This is now in the  procurement phase, and financial close is projected for Spring 2021.

The remainder of the project previously had a projected closing date of “Winter/Spring 2023”, but this is now just “2023”. With the tunnel hived off into a separate contract, it is reasonable that the remainder would have a later start date because the tunnel is a key component that must be in place first.

Metrolinx recently published a Preliminary Business Case for this extension. It includes the following text:

Kennedy Station Pocket Track/Transition Section

The Kennedy transition section extends roughly 550 metres from the east side of the GO Transit Stouffville rail corridor to Commonwealth Avenue and will include special track work and a pocket track to enable every second subway train to short turn to suit ridership demand and minimize fleet requirements, as well as lower operating costs. [p 24]

This turnback has been an on-again, off-again part of the project but it is now clearly included as a cost saving measure. With only every second train running to Sheppard/McCowan, the fleet required (as well as storage) would be within the system’s current capacity. This ties in with the timing of the T1 fleet replacement on Line 2 as there are enough T1s to run alternate, but not full service to Sheppard. This would be similar to the arrangement now used on the TYSSE where only half of the AM peak service runs north of Glencairn Station to Vaughan.

Richmond Hill Subway Extension

The Ontario government recently signed an agreement with York Region for the extension of the Yonge line from Finch to Richmond Hill. The status of this project is unchanged with an RFQ to be issued in Fall 2021, an RFP in Spring 2022 and financial close in Fall 2023.

Sheppard East Subway Extension

This project remains in the planning phase.

Continue reading

Metrolinx Spins Their Tale on the Ontario Line’s Alignment

In a recent article, I reacted to a Metrolinx blog post about the Ontario Line’s design with a series of questions hoping that as the project has now advanced to the Request for Information stage, there would be more details available. Metrolinx chose not to answer, an odd decision for a route about which they are so proud.

Another article has appeared extolling the Ontario Line’s virtues and its benefits for overall capacity on the rapid transit network (all this, of course, with pre-covid assumptions).

The claims in this article clearly were not conjured out of the air, but are based on detailed modelling of the future network. With Metrolinx’ non-response, I will not bother asking question of them, but will simply address their article head on.

Without question, the Ontario Line will provide rapid transit to areas that do not have it today, notably to the northeast in Thorncliffe and Flemingdon Parks and to the major redevelopment node at Don Mills and Eglinton. However, Metrolinx writes as if this was conceived as part of the Ontario Line when the Relief Line North project was already underway under their direction. That planning process was dragging along through an evaluation of alternative alignments most of which made no sense at all, and some of which did not hit these major nodes.

On an historical note, a proposed Queen/Don Mills subway from the 1960s would have gone through these areas. The idea is hardly new.

One might almost think that Metrolinx wanted this process to bumble along as a way to delay the project. Magically, by the time Premier Ford announced the Ontario Line, the always-obvious destination and route had been selected.

As for the west end of the line, yes, it will serve the south end of Liberty Village, but at a considerable walking distance from many buildings in a neighbourhood that has grown north to Queen Street. The problem with east-west service to this area is the capacity of streetcar service provided especially on Queen.

The Ontario Line will begin at the Ontario Science Centre where a new transit hub will connect it to the Crosstown LRT. With LRT trains and TTC buses delivering riders to this station, the Ontario Line will divert more people away from Line 1 than the earlier Relief Line South plan, which would have started near Danforth Avenue at Pape Station.

In fact, Metrolinx projects that the new plan will reduce crowding on Line 1 at Eglinton station by 15 per cent, compared to only 3 for Relief Line South.

In a strange editorial choice, the article illustrates “high-density neighbourhoods that need better transit” with a photo of a small residential street in Riverdale (the corner of Paisley Avenue and Booth Street, near Dundas and Logan) which is roughly midway between proposed stops at Queen and Gerrard Streets.

There is also a photo looking south from Queen Street East on McGee Street, a likely location for the Leslieville Station. Metrolinx does not mention the physical intrusion that expansion of the rail corridor and construction of a station here would produce, only that it makes a connection to the Queen streetcar. Directly behind the photographer is the Jimmie Simpson recreation centre and park which are both threatened by the line. These are conveniently ignored in the article.

Metrolinx is big on connections and travel time savings, but neglects that a rider who is already on the Queen or Kingston Road cars at this location can reach downtown directly simply by staying on board rather than transferring to the Ontario Line.

There is no question that the proposed Relief Line station on Eastern Avenue near Broadview would not make a convenient connection to the GO corridor being well north of the line and very deep so that the tunnel can go under the Don River. That said, this connection was never a principal function of the station, but rather it would serve the East Harbour development site immediately south of the station, and the proposed Broadview streetcar extension through the development would have linked to the Waterfront East streetcar line.

Metrolinx’ true aim both here and at Exhibition Station is quite clear: they need to offload demand from Union Station and hope to do so by diverting riders to the Ontario Line. To make this work, the link between the two routes needs to be as simple as possible, and Metrolinx often refers to the across-the-platform transfers between GO and the OL at East Harbour. That direct transfer is only possible with a surface, not an underground alignment.

However, this assumes a rider is actually destined for the north end of the core business area which, if anything, is moving south from King and across the rail corridor, not north to Queen. GO riders bound for the core area would be better off staying on GO trains, not transferring. There is real irony that Metrolinx trumpets a direct, transfer-free ride to downtown from Don Mills at the same time as they hope to shift GO riders away from Union Station with an extra transfer in their journeys.

This easy connection at East Harbour will give GO Train commuters an option to connect to the subway without going through Union Station – a big part of the reason why this plan will reduce crowding there by 13 per cent.

That’s 13 percent of all riders at Union Station including those arriving on other corridors – Barrie, Kitchener, Stouffville, Richmond Hill – and so this claim represents a very large shift of riders between GO trains and the Ontario Line. This is not credible, especially for outbound connections where the “easy transfer” includes waiting for a GO train running much less frequently than the Ontario Line. (There are also operational issues with the assignment of tracks to services in the shared Lake Shore East corridor, and I don’t think Metrolinx has thought this through.)

When Metrolinx cites the catchment area of stations, they use a distance of 500 metres (a circle one kilometre across). This might work well for a suburban GO station, but in an urban areas, the transit network is more finely grained and a rider could well have a surface route closer-by than a rapid transit station. Access and transfer times consume proportionately more of a trip than in-vehicle times.

The travel time saving brought by the Ontario Line is illustrated in this chart from the project’s website. This chart assumes that access time to an Ontario Line station is the same as the time needed to reach a bus stop, but this is true only for people living very close to the station. At the trip destination, the time from Queen (City Hall Station on the OL) to King & Bay shows the effect of a transfer between rapid transit lines. This almost certainly understates the time penalty. One might well argue that simply walking from the west end of City Hall Station south via Bay to King or via the PATH network (to which the station would connect) would be faster.

This is not to argue against the obvious time and convenience savings of a direct trip, but proportionately the access and transfer times will contribute more than this chart shows for riders who are further from stations at their origin or destination. Metrolinx presents a best case scenario here.

In another recent article, Metrolinx talks about public consultation and the feedback they received from open houses along the route. The overwhelming concern of participants was with the route’s alignment and community effects.

“The Metrolinx team tasked with undertaking the Ontario Line is attuned to the sensitivities of preparing to build in such a vibrant city,” said Franca Di Giovanni, Metrolinx director of community relations for Toronto region. “We take people’s comments very seriously, and making this report public is part of an open and ongoing dialogue around Ontario Line planning.”

However, it is quite clear that Metrolinx is wedded to their alignment and will only “consult” on comparatively minor issues such as station design. Their intransigence to discussions of alternatives is a long-standing problem undermining the credibility of their public participation process.

All of this is slightly surreal in an era when the future of office space and demand to the core is under question. Personally, I prefer optimism that we will get back to something like “normal” eventually, but this will not happen tomorrow. Meanwhile, there will be a huge problem with travel demand outside of the core and on the road network where transit has little hope of competing.

Metrolinx and Infrastructure Ontario have issued an RFI to gauge interest from potential bidders on the Ontario Line project. This process was already delayed due to pushback from industry on the degree of risk transfer the government wanted its “partners” to undertake, and the covid crisis has added to the delay. However, there is a big push to reach a contract signing before the 2022 election. Whether this is practical, and whether any meaningful consultation will actually take place, are open questions.

Metrolinx Mum on Ontario Line Details

A recent Metrolinx blog post extols the virtues of the Ontario Line and the advantages of staying out of underground alignments.

Well, I thought, maybe they are further along in the design and can actually answer some questions about details that have troubled me, among others, for months. I wrote them an email on May 14:

Greetings:

In your recent blog post “The upside of Ontario Line’s upside – How Metrolinx experts are looking to design a Toronto subway that isn’t just confined to dark tunnels” you talk about an elevated alignment on the northern portion of the line through Thorncliffe/Flemingdon, but you state:

“In Leslieville and the Don Lands, the line will run at-grade alongside the existing GO rail corridor, helping to reduce construction impacts.”

One of the issues about this portion of the line has been the question of whether the new trackage would run at the same level as the GO trains, or above them on an elevated structure. This is particularly tricky for the proposed station at Queen Street that requires not just room for the tracks but also for platforms and vertical access to the street below.

Assuming you are still planning to straddle the GO corridor with OL tracks for across-the-platform transfers at East Harbour, this means that there will have to be flyovers/unders where the lines diverge south of Gerrard Station and at the curve north at Corktown.

Here are my questions (some of this is a holdover from the consultation round back when we could still have hundreds of people in a room together):

1. Please confirm whether the OL trackage will be at the same elevation as the GO trackage in the segment between the Don River/East Harbour and the point where the lines diverge at Gerrard Station.

2. How do you plan to handle the need for the eastbound OL track to cross the GO tracks at Gerrard and at Corktown, assuming that you are still planning to have the OL straddle the GO right-of-way? Will the OL eastbound go over or under the GO trackage?

3. How will you handle the station at Queen Street where space is required for platforms and access structures, not just the new OL rails, plus (possibly) one more mainline rail track?

4. Has the requirement for trackage for a possible high speed VIA service leaving Union via Lake Shore East and then the Stouffville corridor been factored into the track requirements yet, and if so, what is the effect?

5. Are there conflicts between a possible GO/Smart Track station at Gerrard and the planned OL structures/station?

6. Has the issue of lateral separation between mainline rail operations and the “lighter” OL vehicles been sorted out? What is the minimum spacing allowed between the two types of service?

Today, May 19, I received the following reply from Nitish Bissonauth, a Media Relations & Issues Specialist at Metrolinx:

Hi Steve,

We have nothing else to provide at this point in time as the project details are still being finalized and the preliminary design business case has yet to be released.

Remember, this is the same Metrolinx that originally expected to have a request for expressions of interest on the street already and a request for proposals in the fall. But they cannot, or rather refuse to answer basic questions that should have been settled long ago. This process has been delayed both by covid-19 and by the reticence of the construction industry to take on the level of risk Metrolinx so fervently wishes to push off of its books.

How people are supposed to intelligently comment with any hope of actual “participation” in the design process is beyond me. This is an organization devoid of any sense of public responsibility answering only to their bosses at Queen’s Park. Fearless Leader doesn’t want surface transit in his Etobicoke bailiwick, but it’s just fine for the folks elsewhere.

It will be amusing to see the pretzel-shaped logic that will appear in the “preliminary design business case” and whether, indeed, it bothers to address the technical challenges of the proposed route. Or will we simply get a line drawn on a map without regard to the local terrain and geography, much like a consultant now working for Metrolinx once did for SmartTrack?

The Transit Nest Egg Toronto Won’t Spend

Between the Scarborough Subway Extension, now rebranded as the Line 2 East Extension, and SmartTrack, Toronto has a lot of money sitting in the bank that could be used to fund other, much more deserving projects.

Ontario has taken over responsibility for the SSE/L2EE, and at least three of the proposed six SmartTrack stations compete directly with the SSE or the Ontario Line. A fourth (at Finch East) would certainly be affected by the SSE running north to Sheppard.

My latest for Now Toronto: Why is city council pretending that SmartTrack is still alive?

Metrolinx Declines to Answer, Again

On Monday, February 3, both my recent NOW Toronto article about the Ontario line and my own Q&A with Metrolinx diving more deeply into the issues appeared.

On the same day, Ben Spurr reported in The Star that members of Toronto Council had learned of private discussions between Metrolinx and interested developers about alternative alignments and station sites. These issues are at the heart of many questions about and objections to the OL plans, and in particular the reluctance, if not outright refusal of Metrolinx to entertain alternatives.

With the Star’s article, Metrolinx can no longer claim that they only have one design, or that alternatives cannot be discussed.

At tonight’s community meeting, on February 5, conveniently a few blocks from my home, I asked Richard Tucker, who is in charge of this project from Metrolinx, point blank what alternatives were on the table.

He responded “Is this for media” and I replied “Of course”.

To which, in turn, Tucker said, in effect, I cannot tell you about that.

If I had merely been an interested member of the community unknown to Metrolinx, who knows what he might have told me, but for official consumption, mum’s the word. This is a senior public servant who simply does not understand (or whose bosses do not understand) the concept of openness, transparency and actual “consultation”.

In many ways, Metrolinx is its own worst enemy with its secrecy and refusal to engage in discussions. This is not confined to pesky media, bloggers and community groups. It is commonly reported by members of Council and the Legislature, not to mention privately by professional staff at the city and TTC.

In the absence of any official pronouncement from Metrolinx, I would be happy to receive information from members of Council who were briefed, or via the tried and true “brown envelope”.

Ontario Line: Many Questions, Few Answers

This article is a companion piece to my article in NOW Toronto Doug Ford’s Ontario Line headed down the wrong track which should be read first as an introduction.

In preparation of that piece, I sent a set of questions to Metrolinx to clarify and expand on many elements of the project. Some of their responses were included in the article, but for limits both of space and complexity, not all of them.

The many duplicate responses (which begin at question 5) are here for readers to see. The text is copied “as is” from a Metrolinx email received on Friday, January 31, 2020. My comments, if any, are in italics after each question and answer.

I look forward to Metrolinx providing more substantive answers to many of these questions before they bother the public with another round of superficial consultation.

Continue reading