TTC Board Meeting July 10, 2018: Part I

The July 10, 2018 meeting of the TTC was its last before the October 22 municipal election. When the new Council meets in early December, it will update the Councillor appointments to this Board and select a new Chair. Whether the existing Chair Josh Colle will return in that role remains to be seen, although he did not sound averse to the idea in his closing remarks. The political balance of the Board will depend on the new Council and on whether the Mayor feels more disposed to a better representation of the centre-left. The new Board’s first meeting will be on December 12, 2018.

The “Citizen” members of the Board (those who are not Councillors) will remain in place until Council deals with appointments to various boards and agencies early in 2019.

The TTC has appointed Rick Leary, who has been Acting CEO since Andy Byford’s departure, to the CEO’s position. Leary had strong support from the Board, and now he must deliver. It will be interesting to see how much of Byford’s style and work, if any, are carried over into this new era. [See Challenges For TTC’s New CEO].

A vital part of the Board’s responsibility (and through them, City Council’s) is a clear understanding of the future needs of transit in Toronto. This is not simply a case of planning a few subway lines, but of understanding how the network as a whole works and what its needs would be under various scenarios. This is especially true when addressing unmet needs of the existing system. From the CEO’s report:

In support of the City of Toronto’s ongoing focus on transformation, the TTC committed in the 2018-2022 Corporate Plan to undertake a comprehensive service review. In addition to assessing efficiency and effectiveness, the study will evaluate how best to provide services mindful of reliability, safety and system integration. Actioning this commitment will help inform deliberations of the newly-appointed Board in 2019. In tandem, as noted last month, we are also preparing an updated and comprehensive long-term Capital Plan that will provide full clarity on the TTC’s long-term capital requirements mindful of legislation, reliability, safety and service standards. The plan will be prepared over the course of 2018 and presented as part of the 2019 Budget process. [p. 8]

This woolly statement could be the basis for better understanding how the Capital Budget works and how its many projects fit together, or this could simply be a rehash of juggling costs back and forth to make the numbers come out right for City financial targets. If the TTC needs more money for bona fide projects, it should say so, and should make the spending levels and timing clear rather than hiding costs “below the line” or beyond the 10-year planning horizon.

Several items on the agenda bear on the TTC’s ability to carry riders, but they were not discussed or presented in that context. This is a fundamental problem for the TTC Board and for the new CEO.

Continue reading

Challenges For TTC’s New CEO

Late in 2011, Andy Byford was hired by the TTC as Chief Operating Officer, a role in which he would understudy the then Chief General Manager, Gary Webster. Little did Byford know that he would inherit the top role faster than planned, in March 2012, after Webster was summarily fired for his failure to support the Scarborough Subway Extension at City Council. The term “to be Webstered” entered the Toronto lexicon as a synonym for what happens to those who speak truth to power.

The position of CGM was renamed as Chief Executive Officer in keeping with common use in business. As such, Byford launched a five-year plan to remake the TTC in his image, a process for which Toronto eventually won the American Public Transit Association’s “Transit System of the Year” award in 2017. Although frequently misrepresented, this award was not for the best transit service on the continent, but for the achievement of a management turnaround plan.

In late 2017, Byford became President of New York City Transit Authority, a role he had long dreamed of having, despite frequent claims in Toronto that he wasn’t planning to leave. This opened the TTC’s CEO position, and the former Deputy, Rick Leary, has been Acting CEO since Byford’s departure.

What challenges does the new CEO face? Broadly, these fall into three categories:

  • The political situation at Queen’s Park is in flux with a new Conservative administration headed by a Premier for whom subways answer every question, and who has talked of shifting responsibility for Toronto’s rapid transit network to Ontario from the City of Toronto.
  • Toronto’s Council and Mayor send mixed signals on transit’s importance for the city’s economic prosperity and the good of its citizens, while keeping the TTC hostage to a tax-fighting dogma that demands ongoing restraint in budget and subsidy growth.
  • The long-term effect of policies by all governments has been a wide gap between the funding needs – both capital and operating – and the money the TTC is actually allowed to spend. Many “big ticket” items are special projects like subway extensions, funded in part for their political benefit, but the hole left in day-to-day project funding continues to deepen.

Underlying all of these is a basic question: what is the TTC supposed to be?

Continue reading

Bombardier Undermines Streetcar Credibility

Updated on July 5, 2018 at 8:00 am: Minor typos corrected. Explanation of replacement service as Flexitys displace older cars clarified.

Over the past day there have been a number of media comments, articles, tweets triggered by the announcement that 67 of Toronto’s new streetcars must return to Bombardier to repair bad welding. This started with an article by Ben Spurr in the Star, with a followup by Spurr and a Globe article by Oliver Moore. I’m sure there are others, but they will do for now.

The problem is described, briefly, in the TTC CEO’s Report released on July 4 as part of the agenda for the Board’s July 10 meeting.

As of June 25, the TTC has 80 Bombardier low-floor streetcars available for service. Unfortunately, we have learned that frame imperfections were found on assembled sections of the 67 vehicles manufactured before 2017 at Bombardier’s facility in Mexico. It is important to note that these welding deficiencies pose no safety threat. Bombardier has agreed to make the required repairs by removing cars from service and sending them to the Bombardier Welding Center of Excellence in La Pocatière, Quebec for repair.

We are working with Bombardier on a repair schedule that will have minimal to no impact on our service to customers. All vehicles will be repaired by the end of 2022.

[From “current issues” on p 6]

There is an inconsistency in the size of the fleet reported by Spurr and repeated by Moore. Although the CEO’s report says they have 80 cars, the number 89 has been used in media reports. This discrepancy is likely due to how Bombardier and the TTC count deliveries. Car 4488 was delivered to TTC Hillcrest today (July 4), and this makes a total of 88 cars in Toronto. (4401 was a prototype and is back at Bombardier for retrofits.) However, the highest car number actually in revenue service, and therefore formally accepted by the TTC, is 4482. This may seem like railfan trivia, but keeping track of just how deliveries are going is an important part of knowing how the roll out of new vehicles is actually progressing day-by-day, not in infrequent updates from the TTC.

The chronology of the problem has also been confused somewhat, and I have to own up to misinterpreting Spurr’s recounting of TTC information until this was sorted out in emails with TTC spokesperson Brad Ross.

  • 2015: TTC and Bombardier identify welding problems at the plant in Mexico where frames for the new cars are manufactured. This was one of the key problems that delayed the early shipments of cars to Toronto. TTC refused to accept cars whose parts would not fit together when they arrived at Thunder Bay for final assembly. In time, this manufacturing problem was corrected, or so it was thought.
  • June 2017 (quoting Spurr): “Company representatives said the problem is a “lack of fusion” in some of the welds on the car’s skeleton, particularly around bogie structures and the articulated portals where different sections of the articulated vehicle are joined. The company says it brought the issue “under control” last June and it won’t be repeated in future deliveries.”
  • October 2017: The TTC becomes aware that repairs would be required according to Ross as quoted by Spurr. One must ask what the TTC’s quality control inspectors were doing in Mexico between June and October.
  • February 2018: 4466, presumably the last car completed with bad parts, is delivered to the TTC. This is a rather long span after Bombardier’s claim that the issue was under control in June 2017.
  • July 2018: TTC and Bombardier announce the need to send the defective cars to a Bombardier plant in Québec which is their “world centre for excellence in welding”. In other words they are giving the job to people who should know what they’re doing.

There is a further inconsistency in that the TTC CEO’s report talks of 67 vehicles manufactured before 2017 in Mexico. This is clearly a typo and the date should be 2018.

If the problem finally escalated to TTC management in October 2017, this was during the Byford era, but there was no report of the problem publicly. If we are to believe tweets from members of the TTC Board, Councillor Mihevc in this case, he was unaware of the need for cars to return to Bombardier until this report broke a few days ago. This begs the question of how much the Board is actually in touch with critical issues on the system they govern.

Teething problems with new equipment are common, although Bombardier has a particularly checkered record in that regard and was dropped from a subway car bid by New York City due to problems with a previous batch of cars. In Toronto, the new TR subway trains continue to have problems, although the worst of these have been ironed out. On subway car orders, riders do not usually see the effect of equipment troubles because the TTC has its older fleet to fall back on, not to mention a generous pool of spare trains, and service gets out to the lines. The streetcar network, starved far too long for new cars, does not have this luxury, and Bombardier’s screwups are in plain sight affecting the transit network.

(One might also recall reliability problems with hybrid buses that could be regularly found parked around the city after going disabled. Again, the full effect is not visible to riders because the TTC maintains a large spare pool to cover for these failures.)

Both Bombardier and the TTC state that the problem is not a safety issue for existing cars, but that over time the poor welds would led to premature failure of cars that are supposed to last 30 years. In a particularly bizarre comment, Bombardier spokesman Eric Prud’Homme is quoted by Moore as saying that this recall spurs interest only because of previous problems with the order and that welding problems are “not uncommon” in the industry. Well, yes, maybe, but when they are on a scale requiring that cars be shipped back to the manufacturer, this is a different problem from minor corrections that can be performed at the customer’s site. And, of course, any retrofit that takes cars out of service reduces the pool available to replace the aging CLRV and ALRV streetcars.

The process is expected to require 19 weeks which is subdivided as:

… 19 weeks total for the repairs: 2 weeks to ship the cars to La Pocatière, 12 weeks for maintenance, 2 weeks to ship back to TO, and then 3 weeks for commissioning. [Tweet from @benspurr]

If the cycle time at Bombardier is 12 weeks (delivery each way and commissioning can take place in parallel with repair work), and there are 17 cycles (4 cars x 17 cycles = 68 cars), then this will take almost 4 years (204 weeks) and will complete in 2022. (I include this detail because the initial impression was that the repairs alone would take 19 weeks, not 12, leading to a mismatch between the proposed end date and the length of the project anyone could calculate.)

If there are only about ten cars out of the fleet at any time (in transit either way, or in commissioning activities when they return), the TTC will get by with the proviso that some of the older cars, likely the smaller CLRVs which although older are more reliable than the ALRVs, will stay in service longer. Ideally, they should be scheduled on peak-only runs so that most of the service is provided by the Flexitys on hand.

Politicians and others with their own agendas have seized on this latest setback to say “maybe we should bus some routes permanently” or just get rid of streetcars. With a hostile government in Queen’s Park, this could be a problem especially if Doug Ford decides to meddle in control of the TTC.

It is important to understand what is possible with the fleet the TTC should have available as well as the planning issues about the streetcar corridors in Toronto.

Buses are now operating on the 505 Dundas and 506 Carlton routes, as well as on a Broadview shuttle replacing a small part of 504 King during track work. Streetcars will return to Carlton in September, possibly with some bus trippers, and likely to Dundas sometime in the fall depending on car availability. 511 Bathurst will revert to bus operation in September because of major construction work on the bus roadway at Bathurst Station, and the 502/503 Kingston Road service will also go back to buses. It should be noted that between them, the peak requirement for streetcars on 502, 503 and 511 is only 28 CLRVs plus spares, and this makes these routes easy candidates for bus substitution because relatively few vehicles are needed for any one route.

The streetcar system has been fleet constrained since the mid 1990s. Ridership losses of the early 90s recession allowed service to be cut back to the point that the 510 Spadina line could open using existing spare cars in the fleet, and the planned rebuild of about 20 PCCs was not required. Since then, there has been no capacity for growing demand, and if anything this has fallen through added congestion on major routes and the gradual decline of fleet reliability and availability. The TTC would like to retire the last of its old cars in 2020, although that may not now be possible.

Toronto is fortunate in that the order for Flexitys represents a considerable addition to potential capacity over the fleet it will replace. The old fleet contained 196 CLRVs and 52 ALRVs. Counting the ALRVs as 1.5 cars, this is the equivalent of 274 CLRVs. The 204 Flexitys counting as 2.0 cars each represent 408 CLRVs. This means that the TTC can improve service capacity rather than simply replacing it one-for-one.

This has been a boon on King Street where the capacity of service provided is now considerably improved even though the number of cars operating has stayed almost unchanged.

The 204-car fleet (or 194 if one takes 10 out of the pool for rotation to Bombardier), can provide service improvements, but it cannot replace the full streetcar service on a 1:1 basis. The table below shows the vehicle requirements for all routes assuming streetcar operation at current service levels, or at a recent level when streetcars were in use. The total cars is 214 which clearly cannot be handled by the Flexity fleet if old cars are substituted 1:1. (Allowing for spares at 20%, the total fleet would have to be 257 cars, and this is roughly the level that an added 60 cars would provide.)

However, that would represent a doubling of capacity on the affected routes, and this is well above what is needed in the short-to-medium term. The tradeoff, if replacement is less than 1:1, is that headways (the time between cars) would widen.

For example, on a 2:3 basis (two new cars for three old ones, a capacity increase of 33%), the fleet requirement would go down by 50 cars (one third of the 153 CLRV/ALRV total below). This would bring the total requirement, just barely, within a 204-car fleet. Headways on affected routes would grow by one third. For example, the peak headway on 511 Bathurst would go from 4.5 to 6.0 minutes. This will inevitably affect ridership just as the replacement of CLRVs by ALRVs did years ago on Queen.

A more generous replacement rate of 3:4 (a capacity increase of 50%) lessens the effect on headways, but requires more cars than are available while maintaining a spare pool of 20%.

An important question is the degree to which additional peak service could be provided by the surviving CLRV fleet, or if bus trippers or replacements are the only viable solution. The smaller the replacement vehicle, the more are required. Moreover, if buses are used, this draws vehicles from an already-strained fleet that cannot meet demands on the bus network.

“Why use streetcars” is a question posed by some. A vital issue for City Planning is that growth in the population and in travel demand will occur disproportionately in the old city and along the streetcar corridors. Service will have to be substantially improved to handle future demand that is expected within the next decade.

The streetcar network once provided considerably more service on some routes than it does today. Demographic shifts and ridership lost to service cuts, not to mention a declining fleet of streetcars, have stretched peak headways in some cases quite substantially. But the capacity is there to carry more riders if only the TTC had the vehicles to operate and the City had the will to fund transit service at higher levels on key routes.  (This is also an issue on the bus network which has its own artificial, budget-driven limitations.)

Ed Keenan, writing recently in The Star, noted that the 506 Carlton car once carried 60,000 riders per day, but has fallen back by 2014, the last year for which the TTC has published ridership stats, to 39,700. In all the hand wringing about the effect of fare systems on ridership, the TTC has lost track of a basic driver of demand: the quality and quantity of service. The infrequent publication of stats does not help in tracking of demand, but even those numbers hide latent demand that simply does not show up out of frustration. The King Street Pilot has shown what can happen when service and capacity improve, and the TTC is proud of their success, but substantial movement beyond King is a political minefield.

Fortunately for Toronto, the streetcar infrastructure is in good shape unlike the situation years back when it declined through less-than-ideal maintenance from which the system has only recently recovered. Likewise, Toronto lost its trolley coaches (electric buses to those too young to remember) in part because the system was allowed to decay by management who wanted rid of this mode and colluded with alternate technology providers to bring this about.

Another requirement for new streetcars waiting in the wings comes from the proposed Waterfront extensions west to Humber Bay and east at least to Broadview. This perennial wallflower project has not attracted funding support, and Waterfront Toronto is reduced to planning for a BRT right-of-way that might, someday, mirror the Queens Quay West design with streetcars.

Toronto’s challenge now will be to decide whether Bombardier can be trusted with an extension to its existing Flexity order (the fastest way to get more cars and build up service), or if a delay to seek bids from other builders is the way to go. In the best political tradition, the Board will consider a recommendation from management that this decision be put off to early 2019 when the financial situation for new streetcars will be clearer.

This brings me to funding from Queen’s Park which is unlikely from an avowed streetcar hater, Doug Ford, now Premier. But, that said, Toronto needs to remember that many capital projects have little provincial money in them, and there is also funding from the Federal government. Toronto needs to decide what it needs, and cobble together funding for its many projects where this can be done. It won’t be easy with competing demands for subway expansion and for the renewal of the existing Line 2 Bloor-Danforth, a great deal of which is “below the line” in the unfunded portion of the City’s capital plans.

Expansion of streetcars or LRT, whatever one might want to call them, has always been an uphill battle in Toronto for various reasons including the idea that streetcars are old fashioned and just  get in the way. Tell that to major cities around the world running and expanding their networks. Toronto needs more capacity to move people on many corridors with easy access to transit, something a few subway lines alone can never achieve. Buses at the density required to replace streetcars will only worsen congestion, not relieve it.

Bombardier, through its ongoing cock-ups with provision of new streetcars, has been no friend to the Toronto system. We must get past this with, if need be, a new supplier of vehicles so that the system can grow. Bombardier’s incompetence should not be used as the justification to retrench and, by implication, eventually dismantle the streetcar network.

 

Broadview Avenue Reconstruction Summer 2018 (Updated July 17, 2018)

This summer, the TTC will rebuild the special work at the intersections of Broadview with Dundas and with Gerrard, as well as replacing the tangent track between these two locations. Minor repairs are also planned between Gerrard and Danforth.

This post will track the progress of the work.

Thursday, June 28, 2018

By the fourth day of the project, the old intersection had been demolished and the new concrete foundation was nearly ready for the new track.

Sunday, July 1, 2018

On day seven, the intersection is fully in place, and work is in progress on various connecting tracks.

 

Wednesday, July 11, 2018

These photos illustrate the first stage in replacing track that was built with the now-standard three-layer technique. At the bottom is a concrete slab, and in the middle layer are steel ties with mount points for Pandrol clips that hold the rail in place. The top  layer of concrete goes from the top of the ties to the rail head.

In the first photo below, the machine is cutting away the concrete between a pair of rails to the depth of the first layer and throwing the spoil into a dump truck. The second photo shows the resulting structure with the rails still in place, but only a narrow band of concrete on either side. In the third photo, the remaining concrete is broken away from the track.

 

Friday, July 13, 2018

The photos below work north from Dundas Street. In some of them, the old track has been removed while it others it remains in place. The last photo shows the result after the track is removed with the connection points for the Pandrol clips exposed but not yet cleaned up for new track installation.

 

Tuesday, July 17, 2018

The photos below show the progress of attaching new rail strings to the pre-existing structure.

In the first and second photos, the attachment points for the Pandrol clips are exposed, but the rail strings have not yet been placed.

In the third photo, the rail is positioned on the ties, and the rubber vibration insulation has been placed around the rail.

In the fourth photo, the clips have been installed locking down the rails.

In the fifth photo, covers have been added over the clips, and concrete work (in the foreground) has already begun. A gauge bar is used to verify the rail spacing. Although the attachment points for the clips effectively dictate the gauge, there is a bit of play, and the rail is checked and adjusted if necessary before the concrete pour.

In the sixth photo, the concrete pour is underway north from Dundas.

Pending Work

The next stage planned from July 23 onward will see the intersection at Gerrard will close for complete reconstruction. 504 King and 505 Dundas buses will shift to use the roads connecting to Gerrard at St. Matthews. 506 Carlton buses will divert via River, Dundas and Logan both ways.

The Tour Tram Debuts in 1973

Forty-five years ago, on June 24, 1973, Peter Witt car 2766 began operating on the streets of Toronto as the Tour Tram. For that first day, the car was decked out with bunting, Canadian and Ontario flags, a Union Jack and photos of HM Queen Elizabeth whose official birthday was celebrated about a week earlier in mid June.

In a previous article, five years ago, I showed the restoration work at Hillcrest Shops. Now, here are photos from on-street operation in the early days. The photos are arranged geographically around the route rather than by date. At the end of the gallery are a few shots of a Tour Tram diversion on Adelaide Street on its third day of operation.

Throughout these photos there are many buildings that no longer exist and views that are now impossible to take because open spaces have been filled in with redevelopment.

King Street Update: May 2018 Data (Part II)

This article continues the analysis of the King Street Pilot with May 2018 data. Part I is in a separate article.

Many topics are covered here, and the intended audience is those readers who want to look at the details of how routes operating on King Street behave. The sections include:

  • Headway reliability on 504 King both in the downtown pilot area and at the terminals.
  • Short turning on the 504 King car.
  • Headway reliability on 514 Cherry and 503 Kingston Road.
  • Headway behaviour for the consolidated 504, 514 and 503 services downtown.
  • A detailed review of 504 King operation on certain days in May 2018.

A common factor through this article is that while travel times in the pilot area have improved thanks to the transit priority scheme, the headways on all affected services are erratic, especially on 514 Cherry and 503 Kingston Road.

The pilot transit project on King is intended to make service more attractive to riders, and this can occur in various ways:

  • Travel times through downtown are shorter and more reliable than during the pre-pilot period.
  • Route capacity has improved partly from schedule changes and recapture of excess travel time, but mainly through the replacement of the older streetcars used on King with larger ones, primarily the new Flexity cars.
  • Headway reliability (consistent times between cars) can be improved if random congestion events are reduced or eliminated, and reliable travel times lessen the need for short turns.

No one change by itself “solves” King Street’s problems, and all three are needed to achieve benefits that will attract riders.

An important part of a transit journey is the time spent waiting for a vehicle. One reason the subway is so popular, aside from its speed, is that trains come frequently and reasonably reliably, although this has become a sore point in recent years. Surface route reliability has always been an issue, and although trips may be faster, there is still the issue of how reliably vehicles actually show up to carry riders.

Continue reading

The Sixth Worst City Myth

Recent stories beginning with the Toronto Sun, and followed by other media including Global, CTV and City, latched onto a claim from a recent study that Toronto was the sixth worst city in the world for commuting. The study from UK’s Expert Market blog writer Sean Julliard combines data from several other sites and indices to formulate a commuting index for 74 cities around the world.

Toronto likes to think of itself as a “transit city” while having severe congestion problems that are regional in scope, not simply confined to the core area which is a tiny fraction of the overall territory covered by this study. That ranking intrigued, but did not surprise me, and I set out to determine just how Toronto ranked so low in a rather long list.

Links to both an Excel and PDF version of the scores and their components are available in Julliard’s article.

First off, it is vital to understand just how these scores were compiled. Here are the components:

  • Metro population: This is the regional population, not necessarily the same as the city population. No source is cited for these values, nor is there a guarantee that other factors are drawn from the same geographic scope. For example, the population given for Toronto is almost 6 million (obviously the GTA), but the price of a monthly farecard is based on the undiscounted value of a TTC Adult Metropass.
  • The following four values come from the Moovit Insights compendium of public transit facts and statistics (Toronto page):
    • Average time spent commuting: These are transit commuting times and have nothing to do with traffic congestion except as it might affect transit vehicles.
    • Average time spent waiting for a bus or a train daily: Again, this is a transit value and appears to be a compendium of all wait times on journeys, not just the initial stage of a trip.
    • Average journey distance: This is a transit journey distance. The value shown for Toronto, 10km, lines up with information from other studies. It is slightly higher than the average for the TTC itself because regional commutes are included in the total. This is a one-way value.
    • Proportion of commuters who have to make at least one change during a transit journey.
  • The following value is derived from the Numbeo Cost of Living index (Toronto page):
    • The percentage of a monthly salary represented by the cost of a monthly transit travel card. In Toronto’s case, this is a salary for Toronto proper, and an undiscounted adult Metropass.
  • The following value is derived from the INRIX Global Traffic Scorecard:
    • Average hours spent in traffic congestion over 240 days (twelve twenty-day months)

Note that most of these factors refer only to transit with only the final one having anything to do with road congestion. This did not prevent many from reporting on how the study showed Toronto with the sixth worst congestion in the world.

Julliard notes that his composite index was primarily based on two factors:

The final ranking is weighted, with cost and time spent commuting judged to be the most important factors.

He does not explain exactly how much weight each factor is given in the total score.

Toronto ranks high on the transit cost component because of our relatively expensive Metropass. Numbeo notes:

Toronto has 13th Most Expensive Monthly Pass (Regular Price) in the World (out of 444 cities).

As for congestion, Toronto sits at 49th place (with 1st being the worst), and its position is rising (bad) thanks to increased time spent by commuters in traffic.

And so we have a sixth worst ranking on Julliard’s scale because we have rotten traffic and expensive transit.

Traffic Congestion

The INRIX scores rank many North American cities, including Montréal (38th), worse off than Toronto for congestion. Los Angeles tops the list with New York (3rd) and San Francisco (5th) not far behind. On a world scale, we are better off than London (7th) and Paris (12th) among many others.

This is a very different view than presented in media reports based on Julliard’s blog.

Transit Indices

Toronto is almost at the bottom of the list for the average time spent commuting by transit at 73rd place out of 74 in Julliard’s list. This is not surprising with a very high 96 minutes spend on average claimed by Moovit. Remember that this is for a round trip, and so their value for the average one-way trip is 48 minutes. That’s a reasonable number for Toronto. It is worth noting that of the 74 cities, only 24 have values of an hour or less. Others in the 90+ list include: Portland, Miami, Istanbul, Philadelphia, Sao Paulo, Birmingham (UK), Salvador (Brazil), Rio de Janiero, Brasilia, and Bogata.

This also begs the question of the scale of transit service in various cities. It is quite likely that in the overall list, it is physically impossible to spend as much time as in Toronto on commute journeys either because the city regions are smaller, or their transit networks do not reach as far as Toronto’s.

For transit wait time, Toronto is much better off at 41st with a relatively low value of 14 minutes. We may take long journeys, but we spend less time waiting to make them.

Our journeys are comparatively long at 10km reflecting the geography of the GTA’s population and work locations, and we sit at 63rd place in the list.

As for transfers, we rank well down on the list at 69th, and that is a direct result of our transit network’s design. Most riders (73%) have to transfer at least once, and given the size of Toronto, that would be hard to avoid except with massive duplication of routes to provide many more one-seat rides. Only 17 cities in the list have a value under 50%, and they tend to be smaller than Toronto with populations averaging 1.7 million (25% of the GTA value).

Toronto is 62nd on the list for cost of a monthly travel card (a TTC Metropass) as a percentage of monthly income at 6.5%. Montreal has a value less than half of Toronto’s, and most cities in Julliard’s list fall below 5%.

Concluding Thoughts

If you want to complain that the TTC costs too much, especially its monthly pass, that’s a valid point, but it has nothing to do with traffic congestion. Travel distances and times are a direct consequence of a region that has, for the most part, built up around a road network, not around transit. Where once the “old” city with its spine of subways and frequent surface routes dominated the travel market, the city region is now overwhelmingly car-based with sprawling populations and job centres to match. This model “worked” when roads had capacity and the assumption that everyone had a car was taken as read. That is not what Toronto has become, and we now have a crisis in transportation network capacity and in the economic viability of so much travel for work and study taking so much time out of everyone’s day.

The Toronto Sun has even taken up the fight against the streetcar again lumping in the downtown know-it-alls who killed the Spadina Expressway with those who preserved the streetcar system. The fact that the vast majority of the GTHA has never seen a streetcar and manages to be hopelessly congested all the same has escaped them. Toronto being “sixth worst” is yet another reason to drag out this hobby horse.

And, of course, some of the greatest congestion lies on our “express” road network. Unlike downtown Toronto, Etobicoke, Scarborough and North York never faced the prospect of demolishing large residential areas in the name of “progress”. A plan to widen the expressways beyond lands long-ago acquired for their construction might teach folks outside of downtown just what provision of adequate road capacity would mean in their own back yards.

Julliard’s study (really a collection of data, but not a “study” in the sense of a detailed review of how the underlying numbers work and what they reveal) is a convenient jumping off point for lazy politicians (and sadly, I must say, for journalists too), but it has been used without context and with even the data it does include misrepresented. If Toronto had a cheaper transit pass, we would have ranked much better, and there would be no story, but this would have no effect on traffic congestion.

Are there problems in the GTA? Of course there are, and they start with a built form and demand pattern that are extremely difficult (impossible in places) to serve with transit. Once the roads are full, they guarantee congestion, and this will not be solved with a few subways or by getting rid of a handful of streetcar lines in Toronto’s core. The “fix” will take time, and must begin with a recognition that shifting people to transit is hard, expensive work. Simplistic, campaign-driven, vote-buying “solutions” are worthless.

King Street Update: May 2018 Data

This article is part of a continuing series reviewing operations on King Street during the transit priority pilot. In Part I here, I review travel times and line capacity in the King Street Pilot’s area. In a follow-up Part II, I will look at headway reliability not just downtown but on the outer ends of the 504 King, 514 Cherry and 503 Kingston Road lines, as well as details of 504 King operation on days when it was badly disrupted.

There has been enough accumulation of data since November 2017 to establish that the pilot has a benefit, although the exact nature varies depending on location, weather and other factors. I will not publish this analysis again until August by which time the effect, if any, of the revised route structure to take effect on Sunday, June 24 will have been in place long enough to accumulate sufficient data. By then there will also be a number of major downtown events to use as reference points in how well the pilot area sustained its transit service.

Continue reading

TTC Plans For a Zero-Emission Bus Fleet

Updated June 13, 2018: Discussion and motions from the TTC Board Meeting added.

At its meeting on June 12, 2018, the TTC board will consider a staff report which sets out in some detail the first stages of Toronto’s migration from diesel and diesel/hybrid buses to a zero-emission fleet.

The TTC’s abrupt shift from diesel to zero-emission followed a July 2017 motion adopting the TransformTO climate change plan which included a reduction target of 80% by 2050. After continued defense of “clean diesel” technology on the basis of cost and reliability, ongoing problems with Hybrid buses, and a view that new technologies were not yet mature enough for system-wide use, the TTC has reversed course and embraced a move to buying only zero-emission vehicles by the mid-2020s. As older vehicles reach end of life, the diesel and hybrid fleets would gradually disappear.

In September 2017 at an unusual Board meeting a vendor, BYD, was given the opportunity to make an extended product pitch as a “deputation”. This led to a more general interest in zero-emission vehicles from two other vendors (New Flyer and Proterra), as well as natural gas alternatives thanks to lobbying by Enbridge Gas.

In November, the Board approved a 30-bus trial with ten vehicles from each of the three vendors, as well as a less definitive study of the role of gaseous fuels.

A major problem through the entire process is that much of this is new technology, and there are many competing claims for its suitability that are not yet substantiated by real world experience. A recent article in the Los Angeles Times details problems with their battery buses and the gap between promises and actual performance.

Toronto is just beginning to learn the cost of moving to a greener fleet and the escalation not only in vehicle costs but in related infrastructure. $50 million has been allocated for those first 30 buses, and a further $88 million is on the table for another 30 plus associated infrastructure. The report is deliberately vague about specific prices for vehicles because negotiations with vendors are still underway.

Without extra investment by other governments, the technology change simply would not happen. In a November 2017 report, TTC staff noted that battery buses were “significantly less expensive” than other options based on the availability of PTIF funding.

Indeed, the current plan is structured to burn through as much of the Federal government’s Public Transit Infrastructure Fund Phase I money as possible. When PTIF was announced, all projects to be part of the first phase were required to be finished by March 2019. This is partly a political date given the election next year, and partly an accounting requirement so that spending occurs within a few fiscal years (government fiscal years start on April 1). The PTIF deadline was extended from 2019 to 2020 when it became obvious that actually spending the new money would not be possible for many cities.

Toronto found itself without projects either in the City or Transit budgets that could soak up the available money in only a few years, and initially the focus was on a massive replacement of the bus fleet to retire the worst of the older buses and, at the same time, shift from an 18-year to a 12-year replacement cycle.

In this context – a subsidy windfall plus an unusually large, multi-year bus order – the opportunity for a fast change in technology presented itself both to the politicians and to the would-be vendors. Whether this will work out remains to be seen, but the TTC is moving cautiously with a trial program that will determine whether the new technologies are credible replacements for what we have today. Meanwhile, the TTC will shift back to Hybrids from Clean Diesel on the premise that Hybrid technology has improved since the less-than-reliable generation of buses they are about to retire.

Recommended Action

The staff report recommends that:

  1. The quantity of electric buses will be increased from 30 to 60 with all vehicles to be delivered by March 31, 2020, and the TTC will work with Toronto Hydro on the design and installation of charging and energy storage systems; the project cost is increased from $50 to $120 million.
  2. The TTC will work with Toronto Hydro to modify one bus garage to accommodate up to 300 buses through the supply of a substation and backup generator at an estimated cost of $18 million.
  3. Staff will provide a project update in first quarter 2019 to the new TTC Board following the Council election in the fall of 2018.
  4. Staff will conduct a feasibility study of all garages and report in the fourth quarter of 2019 on “preliminary estimates for the total costs, benefits, and potential funding opportunities associated with the green bus plan”.

Separately from these reports, staff will present a plan in July 2018 feeding into the 2019 budget process with updated capital plans and tradeoffs necessary to free up money for the new bus infrastructure.

Continue reading

Will Toronto Get More New Streetcars?

Updated June 13, 2018 at 10:00 am: The discussion and actions at the Board Meeting are reported at the end of this article.

Correction June 18, 2018 at 3:45 pm:

The section reporting the debate at the TTC Board meeting originally stated that Acting CEO Rick Leary was waiting to see if Bombardier could ship 20 cars/month by fall 2018 in order to hit the target for contract completion by the end of 2019. This should have read “20 cars/quarter”.

Original Article

Streetcar riders in Toronto are a long-suffering bunch. The size of the fleet has not changed since the mid-1990s despite the addition of a new streetcar line on Spadina in 1997 and the Harbourfront extension to Exhibition Loop in 2000. As the fleet wore out, its reliability dropped, and the now 40-year old CLRVs (single section) and 30-year old ALRVs (two section “articulateds”) are showing their age.

The TTC needed new cars some time ago, and the process of ordering the low floor Flexity fleet goes back to 2006. The first attempt, one that might have brought Toronto new cars about the same size as the ALRVs with a mixture of low and high level floors, was called off when the 100% low floor Flexitys (a design originally for Berlin) became available. That delay, combined with foot-dragging by incoming Mayor Rob Ford, and manufacturing incompetence by Bombardier, has left the TTC with a fleet far below its needs, and new cars straggling onto the property at a glacial rate.

During the past 20 years, population and employment downtown has grown far faster than in other parts of Toronto, and the residential density, once on a downward trend as family neighbourhoods gentrified, is growing. This is not confined to the new south-of-King areas, and is pushing north into the territory of other streetcar lines. The rate of growth is also changing. When the TTC ordered 204 Flexitys, these were expected to handle rising demand through 2027. This date has been revised much earlier to 2020

A major issue for the TTC, and for transit advocates in Toronto, has been the problem of “latent demand”. If the fleet stays the same size or declines, service and capacity follows the same path. The original plan for Flexity roll out onto the streetcar lines focused as much on reducing the number of operators required to carry demand little changed from then-current levels. Now, the TTC acknowledges that growth on streetcar lines went unmet for years.

The 1990s were a critical period because Toronto was coming out of a recession during which the TTC had lost 20% of its ridership, but the streetcar fleet, sized to mid-1990s demand, was unable to expand service as the system recovered. Many of the complaints about “bad streetcar service” come directly from the failure to add capacity as the economy rebounded, and then as the population along streetcar lines began to grow.

Much of the residential growth Downtown between 2012 and 2016 took place south of Queen Street. Almost 50% of all Downtown growth occurred in the King-Spadina and Waterfront West neighbourhoods. The Bay Corridor, King-Parliament and Waterfront Central saw moderate increases accounting for 36% of new residents. As a result of the increase in development in Toronto’s Downtown area, TTC streetcar ridership increased by 20% between 2008 and 2018 which is much higher than what was anticipated back in 2008. Transit mode share across the City has also increased from 23% (2006) to 27% (2016), putting additional pressure on the system.

Recent revision of the projected employment and population growth for Downtown Toronto has introduced higher forecasts which now extend to 2041. The revised estimate of number of new residents in the Downtown is 500% greater than originally projected. The revised estimate of new jobs in the Downtown is 200% greater than originally projected.

The size of the TTC’s streetcar fleet has been unchanged for almost 30 years, during a period of continuously-increasing ridership growth. This has resulted in streetcar capacity, during peak periods, being completely exhausted more than 10 years ago, with no ability to accommodate additional ridership during peak periods. Experience with deployment of the new LFLRVs on the first few streetcar routes has shown that there is an existing unmet, latent demand for peak-travel on the TTC’s streetcar routes. King Street is an excellent example of this. Over the first few months of operation the route experienced an increase of all-day weekday ridership of 16%. There are other factors that have contributed to the ridership increase (such as priority treatments and increased reliability); however, latent demand is one factor driving the ridership increase.

On King Street, the TTC has seen the combined effect of running more capacity (larger vehicles) and more reliable service (the King Street pilot). This number is still constrained by the capacity of service on the street.

On Queen Street, the shuffling of vehicles between routes and the retirement of most of the ALRVs has led, finally, to a schedule that reflects the equipment actually available to operate the route and a net increase in capacity provided, as opposed to scheduled.

Higher-density development is beginning on the Dundas, Carlton and St. Clair routes, and it is spreading away from the central part of the city where the subway is the primary mode.

Future new routes in the eastern waterfront as well as a new link to southern Etobicoke will require even more streetcars.

The TTC projects that by 2033, the peak service requirement will be 287 cars, (345 including spares), equivalent to about 570 (690) CLRVs. At their height, there were only 196 CLRVs and 52 of the larger ALRVs. This is a huge increase in the streetcar system’s capacity, almost to the level of the 745-strong PCC fleet which dominated the system through the 1950s and 60s.

At its meeting on June 12, 2018, the TTC Board will consider a report from staff that summarizes the result of a vendor survey to gauge interest in producing streetcars and proposes the following actions:

Over the coming months, staff will undertake the following:

  1. Request funding approval through 2019 budget process;
  2. Update contract documents based on stakeholder input, contract changes, and lessons learned;
  3. Engage consultant to validate RFI responses (e.g. technical and commercial performance, on-time delivery performance, etc.);
  4. Develop scope and budget for additional maintenance capacity at Hillcrest; and
  5. Report back to the TTC Board in Q1 2019 with recommendations.

The wild card in all of this will be the outcome of the provincial election on June 7, and the degree to which the incoming Premier will support or attempt to sabotage any expansion of streetcar service. Funding arrangements, especially under the federal PTIF scheme, depend on all three levels of government contributing. This effectively gives any one level the ability to veto a project unless there is a change in the rules.