TTC Announces Capital Spending Plan For City Building Fund (Update 2)

Updated January 23, 2020 at 12:10 pm: The TTC has responded to queries about the acquisition of land for new yards for subway lines 1 and 2. The updates are flagged within the text of the article.

Updated January 27, 2020 at 9:30 am: The section on new streetcars has been corrected to state that 60 more cars is the limit on what the TTC could handle, including the use of Exhibition Loop for storage and the renovation of Harvey Shops at Hillcrest as a carhouse for central routes like 512 St. Clair. Previous text stated that 20 was the limit on fleet growth.

The TTC has released a report detailing its planned spending of the newly-allocated funds from Toronto’s City Building Fund. This will be discussed at the TTC Board meeting on January 27, and will go to Toronto Council for incorporation in the 2020-2029 Capital Budget.

Major changes in capital spending include:

  • A return to renewing and upgrading Line 2 Bloor-Danforth as a project for the current decade. This work had been postponed thanks to a lack of funding and, until recently, was replaced with a proposed overhaul of the existing T1 fleet aimed at an eventual lifespan of 40 years. Replacement of the 1960s-era signal system with Automatic Train Control (ATC) has also been restored so that new trains, not to mention the Scarborough extension, can operate under modern technology within this decade.
  • Additional funding for capacity enhancement on Line 1 Yonge-University-Spadina.
  • A large commitment to bus purchases including electric vehicles.
  • Partial renewal of the Wheel-Trans bus fleet.
  • Purchase of 20 new streetcars.

Three quarters of the newly-available funding goes to subway renewal, and even then, the subway projects will require additional money to be completed. Many items in the TTC’s 15 Year Capital Plan remain unfunded, and there are obvious opportunities for generous governments to come to the table and fund aspects of the plan.

Line 2 Renewal

When the TTC deferred the projects associated with Line 2 Renewal, they created a potential collapse of that route thanks to aging vehicles and infrastructure. The T1 trains serving Line 2 were delivered between 1995 and 2001, and replacement of them should have begun in the mid-2020s corresponding to their 30 year design life. The alternative plan to extend this by 10-years depended on an as-yet unproven major overhaul. If the TTC has learned anything from its experience with the streetcar fleet, there are limits to the new life that can be breathed into old equipment especially if the overhaul is more cosmetic than a thorough replacement of technical components.

The other major component of Line 2 Renewal is the replacement of the signal system which dates from the mid 1960’s. If this did not get underway within the coming decade, the TTC could be left with a 65 year old signal system on Line 2 and all of the reliability problems that represents as we know from experience on Line 1. The non-ATC territory on Line 1 dates from the early 1950s (from Eglinton south) to the early 1970s (north to Finch), and problems with this technology are a common source of delays. (ATC will be extended “around the U” from St. Patrick to Queen Station within the first quarter of 2020, and the section from Queen to Rosedale will follow later in the year. Completion to Finch is scheduled for 2022.)

An important factor in plans for Line 2 is the timing of the Scarborough Extension originally planned for 2026, but now pushed out to 2029-30 in Provincial plans. This extension should be built and operated with modern trains and signalling technology, but deferral of the Line 2 Renewal would have meant that the extension to Sheppard would have to be built with provision for co-existence of old and new trains and signalling. This is precisely the sort of plan that complicated the Vaughan extension which, astoundingly, did not include ATC in its original design.

The plan now calls for 62 new trains for Line 2 for delivery between 2026 and 2030. This is a full replacement for the existing fleet and considerably exceeds the 46 peak trains now required for the line even allowing for 20% spares making provision for future growth. There is also the matter of additional trains for the Scarborough extension, although these should be funded by Ontario as part of that project. Whether they actually will be is another matter.

The money allocated from the City Building Fund will only pay for one third ($458 million) of the anticipated cost of the new trains. This is a clear invitation for joint funding from other governments.

The T1 fleet will receive a minor overhaul necessary to extend its life until the new trains arrive.

There is an odd description of this project in the report’s recommendations:

$458 million, representing approximately 1/3 of the 10-year cost for 62 trains, to replace the legacy fleet of T1 trains on Line 2 required for delivery in 2026 through 2030, and which will require an additional $122 million to fund the 1/3 cost between 2030 and 2034. [p 3]

It is not clear whether all of the trains are supposed to arrive in Toronto by 2030 (which would fit with the completion of ATC conversion and opening of the Scarborough extension), or in later years as the funding described above implies. The yearly spending breakdown clearly shows the majority of the spending on new Line 2 trains beyond 2029, and this does not fit with the renewal plans. (See chart at the end of the article.)

The ATC project for Line 2 now lies in the same period as the delivery of new Line 2 trains so that by 2030 the trains, the signals, and the extended subway are all running up-to-date technology.

Line 2 will also require a new carhouse on land that the City of Toronto is acquiring (or may already have bought) southwest of Kipling Station, the old Obico Yard. The plan provides for acquisition and design, but not yet construction which is unfunded.

Updated January 23, 2020: In response to a query about the status of the city’s acquisition of Obico Yard, the TTC replied:

Yes it has already been acquired by the City but the market value assessment is being contested so funds are being secured for potential settlement. We’re also in negotiations to secure a second parcel of land to maintain access to the site. [Email from Stuart Green, Jan. 23/20]

Greenwood Shops will require changes to host new 6-car trains similar to the TRs now operating on Line 1. Originally, the plan was for this yard to be the carhouse for the Relief Line as well as for some of the work car fleet. The detailed plans for Greenwood are not included in this report.

Other funding for Line 2 includes a variety of projects in the state of good repair category that were previously unfunded, but most importantly the upgrade of the power supply system which needs both modernization and additional capacity for projected extra load from more trains.

Even with all of the new money, there is still a funding gap to complete all of the work that has been identified.

Line 1 Renewal and Upgrades

The existing TR fleet serving Line 1 does not require replacement within the timeframe of the Capital Plan, but more trains are needed to provide additional capacity on the route. The report allocates $165 million to one third of the cost of 18 trains to be delivered in 2026-2027. Again, this is a clear budget provision for other governments to come to the table with funding.

The compete conversion to ATC in 2022 will allow a reduction in round trip time on Line 1 so that the existing fleet can provide slightly more frequent service, but the proposed additional trains will allow full exploitation of ATC’s capabilities.

This, however, triggers capacity problems with stations, notably at Bloor-Yonge but also at major stations downtown where the flow of passengers to and from platforms will increase with more frequent service. As on Line 2, there is a need to upgrade power supply systems both to bring infrastructure up-to-date and to provide added capacity for more frequent service.

Also, as on Line 2, there is a gap between the funding allocated and the total cost of various projects.

Line 1 will require a new subway yard, and the TTC proposes to acquire land for it in York Region and design the facility. Why this is part of the Toronto City Building Fund spending is a mystery.

Updated January 23, 2020: In response to a query about Toronto paying for a yard that would be on the Richmond Hill extension, a provincial project, the TTC replied:

Referring to page 14 of the report, it is projected that additional vehicles beyond the 18 trains required in 2026 will be needed for growth of TTC’s existing system. As pointed out, the additional trains serving the Line 1 extension into York Region will also require new facilities for storage and maintenance. The TTC and MX are working together to scope requirements both independently and for a joint solution that meets the needs for Line 1. Whether the land can be found to serve future needs of both Line 1 Extension and TTC’s future growth needs remains to be seen but either way we need to budget for land. [Email from Stuart Green, Jan. 23/20]

Line 4 ATC

The plan include provision of ATC on Line 4 Sheppard. The trains there are ATC-capable, but software changes are required for the 4-car consists to move over the rest of the subway system which is designed for 6-car trains. This becomes an issue once ATC on Line 1 extends north of Davisville Yard where Line 4 trains are serviced.

Buses

The plan allocates $772 million to the purchase of buses and associated infrastructure:

  • $686 million for the procurement of 614 of the estimated 1,575 new buses required over the next decade.
  • $64 million for eBus charging stations at garages.
  • $22 million for the purchase of 232 Wheel-Trans buses of the estimated 498 required.

As with the subway projects, the bus projects require additional funding. There is a further problem in that the existing fleet will reach its retirement age, and without full funding, the number of vehicles available for service will drop precipitously as shown in the chart below.

The TTC has not yet published a consolidated plan for the conversion of its bus garages and fleet from diesel/hybrid to full electric operation, and so we do not know what other capital requirements lurk in future years to complete this work.

Streetcars (Corrected)

The report retains the proposal from the 15 Year plan for 60 more streetcars, but as with many other aspects of the scheme, only allocated funding for one third of this project, or 20 cars. As with so much else in the report, this is a clear invitation for participation by other governments.

These 60 cars would take the TTC to the limit of what it can handle with existing carhouses, including conversion of Harvey Shops as a small carhouse for central routes and the overnight storage of cars at Exhibition Loop.

20 cars would bring the total fleet to 224 assuming that the warranty repairs on the existing fleet will be completed by the time new cars arrive. This would support a peak service of about 186 cars assuming 20% spares, or 26 cars more than the current peak streetcar service. This would allow full restoration of the streetcar system, but would not leave much room for improved service, and the remaining 40 cars in TTC plans should not be ignored, let alone another 40 projected for growth in the 2030 timeframe.

A related issue here is the status of the Waterfront LRT extensions east to Cherry and south to Villiers Island, as well as west to the Humber Bay. More cars will be required for these extensions and that will add to pressure for carhouse space.

Miscellaneous Subway Infrastructure

The plan includes considerable spending in the second half of the 2020s on state of good repair for subway infrastructure. This relieves a looming problem where the subway could begin to fall apart through lack of maintenance and the attempt to worn-out equipment in service. The plan also accelerates work such as asbestos removal as part of overall efforts to improve subway air quality and as a prelude to structural renewal for the aging tunnels.

Overall Spending Plans

The chart below shows the overall capital plan including the detail of the subway infrastructure spending. This is not the total budget, only those portions paid for through the City Building Fund. The TTC’s shopping list for additional contributions is quite clear with many of these lines only partly funded from the CBF.

Indeed, there is an implicit assumption that many of these works can be launched with the expectation of more funding to come, a lot of which is not even required until after election cycles at all level of government. Will our future masters will be more inclined to fund transit?

11 thoughts on “TTC Announces Capital Spending Plan For City Building Fund (Update 2)

  1. This is Unacceptable. It’s time for The TTC to get rid of Rick Leary. H hasn’t done enough in my mind to improve the riders experience on the system. On top of that the TTC needs to look at service in a different manner. Finally Toronto and the GTA need to pass a car or gridlock tax and stop treating transit users less

    Like

  2. Hi Steve, I was just wondering where the Obico yard that the TTC purchased is located? Also, I was on a streetcar recently and noticed that a map titled the Streetcar and Subway Map was posted on the white compartment immediately behind the driver’s seat on the left side of the streetcar facing forward. Upon closer inspection of the map, I noticed that it featured the 900 airport rocket BUS route. Did someone in the TTC’s marketing department mistakenly put the 900 on a Streetcar and Subway map? I’ve also noticed the 900 route being included on the new line 2 subway map which features all the subway stations along line 2 only. What’s with the TTC’s fascination with the 900 airport rocket bus route?

    Steve: Obico Yard is located west of the rail line connecting GO Transit’s Lake Shore West line to the CP at Kipling Station. It used to be a large freight yard.

    The streetcar/subway map has been on the panel behind the operator’s cab on the new cars for some time. The 900 Airport Express has been shown on “rapid transit” maps even longer, and arises from a time when the TTC was tweaking Metrolinx’ nose about the UPX.

    Like

  3. Steve: Line 1 will require a new subway yard, and the TTC proposes to acquire land for it in York Region and design the facility. Why this is part of the Toronto City Building Fund spending is a mystery.

    Because it will be owned and operated by the TTC which is owned by Toronto. Or do you expect the taxpayers of York Region to pay for it and for Toronto to use it for free as you have been using our YRT bus loops for free for decades? If you prefer, then build it in Toronto only York Region was chosen because of lower land costs. The Bombardier plant in Downsview is closing which will leave plenty of room for the Wilson Yard to expand.

    Steve: Dare I mention that York taxpayers uses the subway built to Vaughan for free, their buses use loops at Finch and Pioneer Village Stations for free. Expanding Wilson Yard is not a good operational plan because there are already too many trains concentrated on one side of the “U”.

    York Region needs to learn that they cannot expect Toronto to pay for their transit service.

    Like

  4. I was under the impression the existing carhouses had a comfortable 264 capacity? Has the TTC backpedaled on that?

    Moot point, I can’t see any builder licking their chops to get in on a 20 car order. Why even bother putting that to paper in the plan!

    Steve: The 264 number did not take into account that space at Leslie is needed for it to take over the major repair functions previously done at Hillcrest (oops!). The problem we now face is that this and other projects is only “funded” by Toronto at 1/3 with hopes of contributions from others. This dooms much of the plan to inaction while we wait for money, and Bombardier will simply close up shop. John Tory should be deeply ashamed, and Rick Leary has produced a plan that guarantees most money that does appear will go to his subway projects. There will be handwringing about streetcars, but I am not optimistic we will see any.

    Liked by 1 person

  5. David said: “Upon closer inspection of the map, I noticed that it featured the 900 airport rocket BUS route.”

    Many visitors to the city come by air, and of those, quite a few can use the 900 airport rocket bus. Giving them good directions is more important than making sure that the map title is semantically accurate.

    I’d like to see UPX on the same map too, but TTC is reluctant to put it there, and not because of the feud with Metrolinx. If UPX was on TTC map, some riders would assume it is covered by the TTC fare, which is certainly not the case.

    Steve: Also, the connection to UPX at Dundas West is appalling. Riders should not be encouraged to change there. For that matter, the connection at Kipling is a lot more convenient that at Union, and the bus serves the whole airport, not just one terminal.

    Like

  6. Steve: The 264 number did not take into account that space at Leslie is needed for it to take over the major repair functions previously done at Hillcrest (oops!).

    Between this, the Ashbridge maintenance facility procurement fiasco, and forgetting to design new curves into rebuilt intersections (they better not forget Carlton and Church!) I’m starting to think the people running the streetcar department at the TTC are completely incompetent.

    Steve: Part of the problem is loss of institutional memory, and part the division of responsibility between departments.

    Like

  7. Rick Leary was on Metro Morning on Thursday, after the Wednesday morning mess. Whatever questions he was asked, he kept going back to state of good repair and upgrades to the subway. The repairs will solve all the TTC’s problems, including communication with riders. At least that’s what I got from that.

    As for “streetcah-s”, maybe we might get them perhaps.

    Like

  8. Steve: Dare I mention that York taxpayers uses the subway built to Vaughan for free, their buses use loops at Finch and Pioneer Village Stations for free.

    Built for free? York Region taxpayers paid for their portion of the subway. Uses for free? TTC steals 100% of the revenue from York Region riders when a portion should be shared with the YRT.

    Steve: The agreement forced on the TTC and Toronto was that York would pay proportionately for the municipal portion of the capital cost based on the mileage north of Steeles Avenue, in other words about 40% of the 33% municipal share or maybe 13% of the total. The lion’s share came from provincial and federal taxpayers, not from York Region. York pays nothing toward the operating cost which cost Toronto about $12 million a year after taking into account fare revenue. Most of the riders were already TTC users and so the marginal revenue to the TTC is small. York Region agreed to this arrangement because they got free subway service with no exposure to future costs such as the eventual replacement and expansion of the Line 1 fleet, nor to capital maintenance on the infrastructure.

    Uses the loop at Finch for free? Just in case you are not aware, the YRT/VIVA buses at Finch do NOT use the TTC bus loop/terminal. The YRT/VIVA buses use a separate loop/terminal paid for by the taxpayers of York Region. Uses the loop at Pioneer Village station for free? The taxpayers of York Region paid for the construction of the Pioneer Village station and you seem be unaware that the bus loop/terminal that YRT/VIVA use at Pioneer Village station is situated on the territory of York Region (north of Steeles). Just wondering, have you ever been to Finch or Pioneer Village stations?

    Steve: I have been to both stations, and Pioneer Village in particular is an overblown expensive waste with a difficult transfer connection between anyone on a York Region service to/from a TTC service other than the subway. That’s what you get for having “your own” bus terminal. The only thing that York contributes to the operation of the stations in their territory is to maintain the kiss-and-ride facilities, but the stations are maintained by the TTC with Toronto tax dollars.

    It will be interesting to see who winds up paying for the operation and maintenance of the Richmond Hill extension, most of which is north of Steeles. I would not be surprised if York tries to wriggle out of this.

    Like

  9. Me: The taxpayers of York Region paid for the construction of the Pioneer Village station and you seem to be unaware that the bus loop/terminal that YRT/VIVA use at Pioneer Village station is situated on the territory of York Region (north of Steeles). Just wondering, have you ever been to Finch or Pioneer Village stations?

    Steve: I have been to both stations

    Sorry for questioning whether you had personally visited Finch station and Pioneer Village station and at least the latter is understandable since it is new but the former sounds insulting. Sorry about that.

    Steve: Pioneer Village in particular is an overblown expensive waste with a difficult transfer connection between anyone on a York Region service to/from a TTC service other than the subway.

    Overblown waste indeed but don’t forget that it was a LIBERAL waste. All of the new subway stations as well as the underground crosstown stations are an overblown LIBERAL waste. This is why we elected Premier Ford to cut waste.

    Steve: That’s what you get for having “your own” bus terminal.

    The YRT buses at Pioneer Village station were forced into a separate terminal north of Steeles because of TTC’s overzealousy over potential fare evasions. TTC was worried that YRT buses would bring York Region people into the TTC fare paid zone without them paying any TTC fare. TTC’s relentless announcements and posters say, “There is no excuse not to pay your fare.” But what about when the TTC is so incompetent (as the auditor general found out) that all fare machines on your streetcar are out of service simply because the TTC could not be bothered to empty the coin boxes? There is no excuse not to pay your fare? There are many perfectly legitimate excuses which is why inspectors are given the authority to use discretion. If there were no excuse, then everyone should be fined and even when all streetcar fare machines are out of service simply because the TTC is too incompetent to even empty the coin boxes. It would be nice if the TTC poured as many resources into route management as it does on alleged fare evasion.

    Like

  10. Is there any space to be gained for storing streetcars simply by operating more night service?

    Steve: The TTC is doing this already with 15 minute service on Queen, King and Spadina, and 20 minute service on Carlton. It will be interesting to see if the ridership is a level to justify keeping this service under the productivity standards once the extra service is not required as a “storage” tactic.

    Like

  11. York Region Taxpayer accused TTC of using YRT bus loops for free, implying that this is some kind of a “cheat” of York taxpayers. Some additional information may help explain why this assessment is wrong.

    The bus loops deep in York Region were originally built to accommodate TTC cross-boundary buses that were operated under contract to the local transit agencies, which were later amalgamated into YRT. The bus loops that are closest to Steeles Avenue, however, were originally built by Markham Transit in the 1980’s as part of their request for TTC to extend the north-south bus routes up to Steeles and slightly beyond to serve new residential and employment developments that were happening in south York Region at the time.

    In return for Markham providing these loops near Steeles, TTC extended their routes over the Steeles boundary to the new bus loops, and did not charge any of the operating costs to York Region, nor has it ever charged riders a second fare to cross the boundary on these routes. TTC has also more recently taken on the cost of rebuilding these loops as they need it.

    TTC service that extended deeper into York Region was always done under contract and required charging the second fare, but these cross-boundary routes that serve the local catchment area on both sides of Steeles Ave. were outside of that arrangement. This allowed north-south buses to make a better transfer connection at Steeles and it effectively extended the TTC fare zone a short distance into York Region at very little cost to either TTC or Markham/York Region.

    Rather than being criticized as some kind of nefarious plot by TTC to cheat York Region, it should be celebrated as an example of how a non-political arrangement was able to be put in place decades ago, quietly and efficiently between adjacent municipalities, that continues to benefit transit users on both sides of the boundary.

    With regard to Pioneer Village Station, Don indicated that YRT was “forced” into a separate bus terminal north of Steeles because the TTC was overly worried about fare evasion in a single, joint bus terminal. I don’t know where he got this information, but it is incorrect. TTC already has several bus terminals that are used by non-TTC buses, including Don Mills and Sheppard West Stn (YRT/Viva), Islington Stn (MiWay), and Scarborough Centre Stn (GO), which have operated that way for decades.

    At Pioneer Village Station, York Region already owned property north of Steeles, but it was not large enough to accommodate both YRT and TTC buses. The option of a single bus terminal, either north or south of Steeles was looked at, but neither Vaughan nor York University were willing to sacrifice more development land for a bigger, single bus terminal. The only other option was to build two smaller bus terminals on either side of Steeles Ave. Note that the TTC bus terminal is located directly above the subway tunnels to preserve as much unencumbered development land around the station as possible. As is often the case in these big projects, no one ever gets everything that they want and, in this case, what was sacrificed for the benefit of future development, was the transfer between YRT and TTC buses, which was expected to be a lesser demand, relative to the bus-subway transfer.

    Not everyone has to agree with it, but the two-terminal solution was a rational outcome arrived at through agreement by people on both sides of the municipal boundary — it had nothing to do with TTC forcing or “victimizing” anybody.

    Liked by 1 person

Comments are closed.