Will the TTC Presto Project Ever End? (Updated)

Updated March 19, 2019 at 4:00 pm: The TTC has replied to questions I sent about the new Presto spending. There is a major change in project scope.

Buried in hundreds of pages of the TTC’s Capital Budget are a few sheets on the implementation of Presto, the fare system foisted on Toronto by Queen’s Park.

According to the project description, the estimated final cost (EFC) for the TTC would be $44 million (this is net of subsidies from other levels of government). However, as the project budget shows, $43 million was spent to the end of 2017, and a further $19.4 million in 2018. Most of the costs booked to date have been under the category of “Project Management”.

The project is supposed to wind up in 2019, but there is a budgeted TTC cost of $17.3 million.

And lo and behold! In 2020 there is a further $49 million.

Both the 2019 and 2020 spending are net new in the budget this year, although $47 million of the 2020 amount is still considered to be “unfunded”.

On March 5, 2019, I asked the TTC what this proposed spending was to cover considering that the Project Summary (below) is silent on this new money.

And so a question for everyone who is following the Presto story: Why is there a total of $66.3 million in new money included in the 2019-2028 Capital Budget that was not there last year? What will it pay for? Will this spending ever end, or are will Toronto continue to discover costs for Presto it missed when the project to adopt this system was sold to the TTC Board and Council?

The TTC Replies:

A portion of 2019 added funding is to enable TTC farecard staff to continue work on PRESTO implementation (products, service standards, etc.)  There is also a portion of unspent 2018 funds carried forward into 2019.

Some 2019 costs and the 2020 cash flow is a preliminary estimate for the cost of an on vehicle ticket solution for buses that will allow customers to pay with cash to obtain a ticket that will allow them to pass through faregates.  This is a very early estimate that was developed as part of the comprehensive list of projects identified in the Capital Investment Plan.  As noted, aside from initial funds for a feasibility study this project is not funded.

The 2019 funding increase was two part:

a) Continued PRESTO implementation costs

The PRESTO rollout was anticipated to be substantial complete in 2018 with the rollout of the PRESTO Ticket product, and solutions for cross boundary travel, downtown express travel and other PRESTO payment products. MX was unable to deliver these items, particularly PRESTO Tickets, as expected in 2018 and delayed the implementation to 2019. Resources were also added to the capital program to addresses software quality and system performance issues. Additional capital funds were requested to accommodate and support the continued work and change to the PRESTO implementation plan.

b) Commence initial Cash on Surface (Farebox Replacement) work

A solution is required to allow cash paying customers transferring from surface vehicles (buses, streetcars, Wheel Trans) to enter non-integrated TTC stations with fare gates. Initial capital funds were added to year 2019 and 2020 as a very early estimate that was developed as part of the comprehensive list of projects identified in the Capital Investment Plan.  This funding is for business case development and feasibility analysis only.

We had also added funds for the development of a fare payment solution for Wheel Trans contracted taxis in the event Metrolinx/PRESTO was unable to do so.

[Email from Stuart Green, March 19, 2019]

In the Project Expenditure Summary (third page below), the section “Budget Comparisons” includes three lines:

  • “B”: Approved budget figures from the 2018 Capital plan
  • “P”: Proposed budget in the 2019 Capital plan
  • “C”: Change from 2018 approval

The planned spending in 2018 was $10.6 million, but this is revised to $19.5m showing the change in the year just completed. New spending of $17.3m and $49.0m are proposed for 2019 and 2020. There is an offsetting entry elsewhere in the budget reducing the 2020 approval to only $2m.

This is a very large change in the scope of the project and shows the degree to which features that should have been included in the base Presto functionality are missing either because the TTC didn’t ask for them, or because Metrolinx intends to charge for their implementation. This will be of interest to the Auditor General’s review of the Presto contract now underway.

10 thoughts on “Will the TTC Presto Project Ever End? (Updated)

  1. I hope you mean $43 million spent through end of 2017, not $43 billion.

    Steve: Ooops, yes. Even Presto could not burn through that much!

    Like

  2. I notice at the bottom of the last pdf the note “FINITE” and an end date of 2020. Of course, we know that the City & TTC will simply move the date forward as necessary!

    Like

  3. According to the project description, the estimated final cost (EFC) for the TTC would be $44 million (this is net of subsidies from other levels of government). However, as the project budget shows, $43 million was spent to the end of 2017, and a further $19.4 million in 2018. Most of the costs booked to date have been under the category of “Project Management”.

    The project is supposed to wind up in 2019, but there is a budgeted TTC cost of $17.3 million.

    And lo and behold! In 2020 there is a further $49 million.

    [Remainder of quotation clipped by Steve.]

    One has to wonder: Which is worse? Their not having an answer because they know something, or not answering because they haven’t a clue.

    There’s perhaps irony in that it’s not far off the $64M claimed by the AG for evasion and glitches:

    Like

  4. $43 Billion – should be million, yes?

    And the extra funds must be for the newly required fare enforcers?

    Steve: Yes, million as Normal Wilson pointed out in another comment. Fixed with thanks to both of you.

    The fare enforcement is a staff cost which is in the Operating Budget, not Capital.

    Like

  5. If it was not for Steve, we would never know that the TTC wasted 43 BILLION dollars on Presto already with more waste to come. Thanks Steve for letting us know. This is why the province needs to take over the TTC.

    Steve: The “Billion” was a typo that has been fixed. It is “Million”. And don’t forget that Presto is a provincial project that has cost us hundreds of millions already.

    Like

  6. There’s a lot of text in the years-old TTC/Metrolinx agreement about operators being able to give people Presto-enabled transfers.

    How then is there any new costs related to this?

    Steve: That is precisely my point. TTC seems to get dinged for the cost of implementing things that are already in their contract, in part because they won’t publicly shame Metrolinx for non-performance.

    Like

  7. What is your take on the Trudeau budget? There is no money for the Downtown Relief Line, there is no money for the Waterfront East LRT, there is no money for the Waterfront West LRT, there is no money for the 60 more streetcars that Toronto needs, there is no money for any of the much needed transit projects in the GTHA. I personally am very disappointed by the Trudeau budget. What do you think?

    Steve: The big ticket transit projects will be funded out of the Public Transit Infrastructure Fund, Phase II, which is already built into the budget from past announcements. Many projects’ update reports are coming to the next round of Toronto Executive and Council in April, and arising from this the City will sort out how it wants to use Toronto’s share of the money. Even so, the amount of PTIF available is well below the total of all projects. Then there is teh small of problem of getting Queen’s Park to chip in the provincial share.

    Like

  8. In my random trips around the TTC in the past couple of days (paying with tokens from a found stash), I have seen several examples of on-vehicle Presto readers reading ‘Ready’, but not reading Presto cards — i.e. the person taps, repeatedly, but there is neither an Accepted or Rejected. Sometimes the person can tap in at the back door reader instead, sometimes not. The same Presto reader might read most cards, then not read another one or two — which are valid, because the person then taps on the other reader.

    I have doubts about the longevity of the $6 Presto cards. In my opinion, Presto should be providing them for free, which would give them an incentive to make them simple and reliable.

    Steve: Meanwhile, I have seen actual working (!!!) single ride vending machines successfully taking token and cash fares, and printing receipts, all without repeated attempts to make them take the coins, freezing up for riders or generally being cantankerous. Maybe it’s spring and they are in a good mood!

    Liked by 1 person

  9. Presto was foisted on Toronto by the previous provincial government, and I expect that the current occupant of Queen’s Park will simply foist any extra payments for Presto on Toronto.

    Like

  10. “I have doubts about the longevity of the $6 Presto cards.”

    I have cracked quite a few in the past six or seven years. You don’t need even a full crack to stop them from working, even a hairline crack in a corner will bork it. It’s one of the reasons I simply won’t take it out of my briefcase anymore for streetcar rides, despite the loud sighs from fare inspectors who don’t like the fact I know I don’t have to tap on since I have a pass loaded. I’m not interested in paying $6 once again.

    Liked by 1 person

Comments are closed.